2275 N LAKE SHORE AVE 90039

Certificate Information: 2275 N LAKE SHORE AVE 90039

Application / Permit
25014-10000-02808
Plan Check / Job No.
B25LA25506
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Convert existing crawl space to livable area resulting in two story single family dwelling
Permit Issued
Issued on 1/30/2026
Issuing Office
Current Status
Issued on 1/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 JESSE VIDUYA
Corrections Issued 7/16/2025 JESSE VIDUYA
Quality Review Completed 7/22/2025 CHAD DOI
Applicant returned to address corrections 10/30/2025 JESSE VIDUYA
Applicant returned to address corrections 11/12/2025 JESSE VIDUYA
Applicant returned to address corrections 12/19/2025 JESSE VIDUYA
Plan Check Approved 1/26/2026 JESSE VIDUYA
Issued 1/30/2026 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/1/2025 TREVOR QUAN
BHO/Hillside ordinance Cleared 8/1/2025 TREVOR QUAN
BHO/Hillside ordinance Cleared 8/1/2025 TREVOR QUAN
BHO/Hillside ordinance Cleared 8/1/2025 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/4/2025 TREVOR QUAN
Hydrant and Access approval Cleared 8/6/2025 PATRICK PEREZ
GPI Written Notices Cleared 12/19/2025 JESSE VIDUYA
Grading Pre-Inspection Cleared 1/26/2026 ROBERT PINA

Contact Information

Contractor Superior Home Remodeling Inc; Lic. No.: 1048870-B       ,
Engineer Hayrikian,, Arsham; Lic. No.: C91446 1732 CAMULOS AVE      GLENDALE, CA 91208
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,
Geologist Miller,, Steven; Lic. No.: EG1303 23890 COPPERHILL DRIVE #111      VALENCIA, CA 91354

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/20/2026 Partial Inspection HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 3/6/2026 Conditional Approval OSVALDO PARAMO
Footing/Foundation/Slab 3/9/2026 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/17/2026 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 4/2/2026 Conditional Approval GEM DE OCAMPO
Footing/Foundation/Slab 4/2/2026 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 4/8/2026 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/10/2026 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/8/2026 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/8/2026 Approved HAMIK HARTOUNIAN
Green Building Rough 5/8/2026 Approved HAMIK HARTOUNIAN
MERV13>=Rough 5/8/2026 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 5/8/2026 Approved HAMIK HARTOUNIAN
HVAC-Rough 6/1/2026 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/9/2026 Partial Approval ALIZAH MAYAGOITIA
Insulation 6/9/2026 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/16/2026 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/22/2026 Partial Approval HAMIK HARTOUNIAN
Shower Pan 7/22/2026 Approved HAMIK HARTOUNIAN