3228-3230 S CORINTH AVE 90066

Certificate Information: 3228-3230 S CORINTH AVE 90066

Application / Permit
25014-10000-02804
Plan Check / Job No.
B25LA25472
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN- ADDITION TO EXISTING SINGLE FAMILY DWLLING UNIT. ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/28/2025
Issuing Office
Current Status
Issued on 11/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2025 APPLICANT
Assigned to Plan Check Engineer 6/24/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 6/25/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 10/28/2025 ARAMIK SHAHMIRZAIAN
Applicant returned to address corrections 11/12/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 11/26/2025 ARAMIK SHAHMIRZAIAN
Issued 11/28/2025 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 7/26/2025 JESUS CISNEROS
Eng Process Fee Ord 176,300 Cleared 10/14/2025 JESUS CISNEROS
Specific Plan Cleared 10/21/2025 EDER ROMERO
Roof/Waste drainage to street Cleared 10/23/2025 TONY CHIANG
Grading Pre-Inspection Cleared 10/23/2025 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/30/2025 Corrections Issued WILBER ROSALES
Footing/Foundation/Slab 12/30/2025 Corrections Issued WILBER ROSALES
PLUMBING-Rough 12/30/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 1/8/2026 Conditional Approval KIRK SANDERS
PLUMBING-Rough 1/8/2026 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Partial Approval DANIEL VERA
Insulation 1/21/2026 Partial Approval DANIEL VERA
Underground Mechanical 1/21/2026 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Partial Approval ANTHONY EGSON
Deputy Drilled-In Anchors 1/27/2026 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 2/18/2026 Partial Approval WILBER ROSALES
PLUMBING-Rough 2/18/2026 Corrections Issued WILBER ROSALES
Pre-Inspection 2/25/2026 Partial Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 3/16/2026 Conditional Approval ARAM AVEDISIAN
Wood Frame 3/17/2026 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2026 Partial Approval RYAN SALAZAR
HVAC-Rough 3/24/2026 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 3/24/2026 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/3/2026 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 4/3/2026 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/3/2026 Corrections Issued EUGENE CASSIDY
Shower Pan 4/3/2026 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/9/2026 Approved RYAN SALAZAR
ELECTRICAL-Rough 4/9/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/9/2026 Approved RYAN SALAZAR
MERV13>=Rough 4/9/2026 Approved RYAN SALAZAR
Insulation 6/1/2026 Partial Approval KIRK SANDERS
Drywall Nailing 6/18/2026 Approved KIRK SANDERS