6115 W GLEN OAK 90068

Certificate Information: 6115 W GLEN OAK 90068

Application / Permit
25014-10000-02798
Plan Check / Job No.
B25LA22600
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to (E) SFD . Reconfigure interior floor plan layout .
Permit Issued
Issued on 7/16/2025
Issuing Office
Current Status
CofO Issued on 1/8/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 JOE VO
Corrections Issued 6/10/2025 JOE VO
Quality Review Completed 6/11/2025 PRANITA SHAH
Plan Check Approved 7/15/2025 JOE VO
Issued 7/16/2025 APPLICANT
CofO in Progress 1/6/2026 CRAIG VAUGHAN
CofO in Progress 1/7/2026 SCOTT FINNILA
Permit Finaled 1/8/2026 DEROLD HAUFF
CofO Issued 1/8/2026 DEROLD HAUFF
Permit Finaled 1/8/2026 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 6/18/2025 RUBEN VASQUEZ
Address approval Cleared 7/2/2025 DAVID LOPEZ
Highway dedication Cleared 7/2/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 7/2/2025 DAVID LOPEZ
Sewer availability Cleared 7/2/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/7/2025 DAVID LOPEZ
Hydrant and Access approval Cleared 7/7/2025 JERRY KAO
Grading Pre-Inspection Cleared 7/15/2025 JOE VO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/13/2025 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 8/13/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 8/13/2025 Not Ready for Inspection CRAIG VAUGHAN
Piling/Pier/Caisson 8/13/2025 Not Ready for Inspection CRAIG VAUGHAN
Sewer 8/13/2025 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 8/14/2025 Approved DAVID WILLIAMS
Underground Mechanical 8/14/2025 Partial Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 8/22/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 8/22/2025 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 9/16/2025 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval CRAIG VAUGHAN
Green Building Rough 9/16/2025 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 9/16/2025 Not Ready for Inspection CRAIG VAUGHAN
Sewer 9/16/2025 Approved CRAIG VAUGHAN
Underground Mechanical 9/16/2025 Approved CRAIG VAUGHAN
Wood Frame 9/16/2025 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/18/2025 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 9/18/2025 Not Ready for Inspection CRAIG VAUGHAN
Shower Pan 9/18/2025 Not Ready for Inspection CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 9/19/2025 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/23/2025 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 9/23/2025 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 9/23/2025 Approved CRAIG VAUGHAN
Deputy Wood Construction 9/24/2025 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 9/25/2025 Approved CRAIG VAUGHAN
Green Building Rough 9/25/2025 Approved CRAIG VAUGHAN
HVAC-Rough 9/25/2025 Partial Approval CRAIG VAUGHAN
Insulation 9/30/2025 Approved CRAIG VAUGHAN
Shower Pan 9/30/2025 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 10/2/2025 Partial Approval CRAIG VAUGHAN
Shower Pan 10/2/2025 Approved CRAIG VAUGHAN
Drywall Nailing 10/9/2025 Corrections Issued CRAIG VAUGHAN
Interior/Exterior Lathing 10/9/2025 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 10/10/2025 Approved CRAIG VAUGHAN
Drywall Nailing 10/28/2025 Approved SCOTT FINNILA
ELECTRICAL-Rough 10/28/2025 Approved SCOTT FINNILA
HVAC-Rough 10/28/2025 Approved SCOTT FINNILA
ELECTRICAL-Final 12/5/2025 Approved ENRIQUE MIRELES
Final 12/5/2025 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 12/5/2025 Approved ENRIQUE MIRELES
HVAC-Final 12/5/2025 Approved ENRIQUE MIRELES
PLUMBING-Final 12/5/2025 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/5/2025 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 12/5/2025 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 12/5/2025 Approved ENRIQUE MIRELES
Final 12/29/2025 Corrections Issued CRAIG VAUGHAN
Final 12/31/2025 OK to Issue CofO CRAIG VAUGHAN
Final 1/5/2026 OK to Issue CofO CRAIG VAUGHAN