714 N AVENUE 64 90042

Certificate Information: 714 N AVENUE 64 90042

Application / Permit
25014-10000-02779
Plan Check / Job No.
B25LA25265
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED CONERSION OF SFD TO ADU WITH ADDITION
Permit Issued
Issued on 12/4/2025
Issuing Office
Metro
Current Status
Issued on 12/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 7/3/2025 SINA KHOSRAVI
Corrections Issued 7/25/2025 GEORGE JOLAKIAN
Quality Review Completed 8/1/2025 KEN GILL
Building Plans Picked Up 8/4/2025 APPLICANT
Applicant returned to address corrections 9/23/2025 SINA KHOSRAVI
Plan Check Approved 11/26/2025 SINA KHOSRAVI
Issued 12/4/2025 APPLICANT

Permit Application Clearance Information

CPC Cleared 9/23/2025 DANIEL CORONADO
Address approval Cleared 9/26/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 9/26/2025 DERRICK MAGEE
Sewer availability Cleared 9/26/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 10/6/2025 TREVOR QUAN
HPOZ Cleared 11/18/2025 NATHALY DE LA PAZ
Grading Pre-Inspection Cleared 11/26/2025 GEORGE JOLAKIAN

Contact Information

Contractor Hicon Llc; Lic. No.: 1080894-B 255 NORTH ALLEN STREET      SAN BERNARDINO, CA 92408
Engineer Nguyen,, Lam Thanh; Lic. No.: C36957 3338 PUNTA ALTA STE 2B      LAGUNA WOODS, CA 92637

Inspector Information

No Data Available.

Pending Inspections

Green Building Rough 6/12/2026   
Drywall Nailing 6/12/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/22/2025 Corrections Issued DAVID WILLIAMS
Footing/Foundation/Slab 2/11/2026 Approved DAVID WILLIAMS
ELECTRICAL-Rough 4/28/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 4/28/2026 Corrections Issued DAVID WILLIAMS
Sewer 4/28/2026 Partial Approval DAVID WILLIAMS
Wood Frame 4/28/2026 Partial Approval DAVID WILLIAMS
Insulation 5/8/2026 Corrections Issued ALEX COLIN
Wood Frame 5/13/2026 Corrections Issued DAVID WILLIAMS
BUILDING-Rough-Frame 6/1/2026 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 6/1/2026 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 6/1/2026 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 6/3/2026 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 6/3/2026 Corrections Issued DAVID WILLIAMS
Green Building Rough 6/3/2026 Not Ready for Inspection DAVID WILLIAMS
HVAC-Rough 6/3/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 6/3/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 6/5/2026 Approved NICHOLAS LOPEZ