2956 S KELTON AVE 90064
Certificate Information: 2956 S KELTON AVE 90064
- Application / Permit
- 25014-10000-02764
- Plan Check / Job No.
- B25LA25111
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: Major remodel and irregular shape addition to 1st floor with 2nd floor. NFPA 13D SPRINKLERED REQUIRED THROUGHOUT. ***SEE COMMENTS***
- Permit Issued
- Issued on 3/27/2026
- Issuing Office
- Current Status
- Issued on 3/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | JAHANSHAH POURHASSAN |
| Corrections Issued | 6/22/2025 | JAD BASMA |
| Quality Review Completed | 6/24/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 12/8/2025 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/16/2025 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/19/2025 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 12/30/2025 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/8/2026 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/10/2026 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/13/2026 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/27/2026 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 3/10/2026 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 3/12/2026 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 3/25/2026 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 3/27/2026 | JAHANSHAH POURHASSAN |
| Issued | 3/27/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/23/2025 | JEFF LOREDO |
| Specific Plan | Cleared | 9/23/2025 | EDER ROMERO |
| Grading Pre-Inspection | Cleared | 9/23/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2025 | JEFF LOREDO |
| ZA Case | Cleared | 9/26/2025 | GEORGIA SMITH |
| Sewer availability | Cleared | 12/15/2025 | JESUS CISNEROS |
| Specific Plan | Cleared | 12/17/2025 | RUBEN VASQUEZ |
| GPI Written Notices | Cleared | 3/25/2026 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| BUILDING-Rough-Frame | 6/10/2026 |
| MERV13>=Rough | 6/10/2026 |
| Green Building Rough | 6/10/2026 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2026 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 4/13/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/13/2026 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 4/29/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2026 | Partial Approval | RYAN SALAZAR |
| MERV13>=Rough | 4/29/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 5/5/2026 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 5/5/2026 | Partial Approval | EUGENE CASSIDY |