3144 W ATWATER AVE 90039

Certificate Information: 3144 W ATWATER AVE 90039

Application / Permit
25014-10000-02761
Plan Check / Job No.
B25LA25081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NEW ATTACHED DECK.
Permit Issued
Issued on 7/28/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 KEVIN MORALES
Corrections Issued 6/24/2025 KEVIN MORALES
Quality Review Completed 6/25/2025 EUGENE BARBEAU
Plan Check Approved 7/23/2025 KEVIN MORALES
Issued 7/28/2025 APPLICANT
CofO in Progress 4/27/2026 NICHOLAS LOPEZ
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/3/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/3/2025 MICHAEL BROWN
Sewer availability Cleared 7/3/2025 MICHAEL BROWN

Contact Information

Contractor Pnr Builders Inc; Lic. No.: 1028148-B       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/15/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 9/10/2025 Partial Approval NICHOLAS LOPEZ
Underground Mechanical 9/10/2025 Partial Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 9/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 10/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Rough 10/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 10/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Partial Approval JOSH MEISTER
Green Building Rough 10/29/2025 Not Ready for Inspection JOSH MEISTER
Pre-Inspection 10/29/2025 Not Ready for Inspection JOSH MEISTER
Rough-Elec/Plmb/HVAC 10/29/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 11/4/2025 Approved NICHOLAS LOPEZ
Green Building Rough 11/4/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 11/4/2025 Partial Approval NICHOLAS LOPEZ
Insulation 11/12/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 11/18/2025 Approved NICHOLAS LOPEZ
Shower Pan 12/24/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Approved NICHOLAS LOPEZ
Gas Test 4/13/2026 Approved NICHOLAS LOPEZ
Final 4/22/2026 Corrections Issued NICHOLAS LOPEZ
Footing/Foundation/Slab 4/22/2026 Approved NICHOLAS LOPEZ
Green Building Final 4/22/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 4/22/2026 Approved NICHOLAS LOPEZ
Final 4/24/2026 OK to Issue CofO NICHOLAS LOPEZ