1735 S HAYWORTH AVE 90035
Certificate Information: 1735 S HAYWORTH AVE 90035
- Application / Permit
- 25014-10000-02731
- Plan Check / Job No.
- B25LA24849
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION AT THE REAR AND INTERIOR ALTERATION TO AN (E) SINGLE STORY SFD. WORK PER WFPP.
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2025 | NGHI SU |
| Corrections Issued | 6/23/2025 | NGHI SU |
| Building Plans Picked Up | 6/25/2025 | APPLICANT |
| Plan Check Approved | 7/10/2025 | SERGIO GUTIERREZ |
| Issued | 7/15/2025 | APPLICANT |
| CofO in Progress | 1/20/2026 | BRENDAN MORELLI |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
| CofO Issued | 1/21/2026 | DEROLD HAUFF |
| Permit Finaled | 1/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/27/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Elite Construction And Cabinets Inc; Lic. No.: 1131283-B | 1819 BELCROFT AVENUE SOUTH EL MONTE, CA 91733 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/17/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 8/20/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 8/22/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 8/22/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 8/22/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 8/22/2025 | Approved | ARTHUR NEGRETE |
| Wood Frame | 8/22/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Insulation | 8/27/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 8/28/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 8/28/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 9/3/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 1/7/2026 | Approved | JOSH MEISTER |
| Final | 1/7/2026 | Corrections Issued | JOSH MEISTER |
| Footing/Foundation/Slab | 1/7/2026 | Approved | JOSH MEISTER |
| Green Building Final | 1/7/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Rough | 1/7/2026 | Approved | JOSH MEISTER |
| METHANE-Barrier | 1/7/2026 | Approved | JOSH MEISTER |
| METHANE-Final | 1/7/2026 | Approved | JOSH MEISTER |
| METHANE-Rough | 1/7/2026 | Approved | JOSH MEISTER |
| METHANE-Subgrade | 1/7/2026 | Approved | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Not Ready | JOSH MEISTER |
| Smoke Detectors | 1/7/2026 | Approved | JOSH MEISTER |
| Final | 1/15/2026 | OK to Issue CofO | BRENDAN MORELLI |
| Green Building Final | 1/15/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | BRENDAN MORELLI |