1544 W 215TH ST 90501
Certificate Information: 1544 W 215TH ST 90501
- Application / Permit
- 25014-10000-02717
- Plan Check / Job No.
- B25LA24614
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ADDITION TO (E) 1-STORY SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 7/18/2025
- Issuing Office
- Current Status
- CofO Issued on 1/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2025 | LUKE GONZALES |
| Corrections Issued | 6/18/2025 | LUKE GONZALES |
| Building Plans Picked Up | 6/26/2025 | APPLICANT |
| Plan Check Approved | 7/18/2025 | CARLOS MONTES |
| Issued | 7/18/2025 | APPLICANT |
| CofO in Progress | 1/22/2026 | EUGENE CASSIDY |
| Permit Finaled | 1/23/2026 | ANSON MAGLASANG |
| CofO Issued | 1/23/2026 | ANSON MAGLASANG |
| Permit Finaled | 1/23/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2025 | DERRICK MAGEE |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pinzon,, Eduardo Andres; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/1/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/5/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2025 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/11/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/11/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/5/2025 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 9/5/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Underground Mechanical | 9/5/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/18/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/18/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 9/18/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 9/18/2025 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 9/18/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/8/2025 | Approved | EUGENE CASSIDY |
| Insulation | 10/8/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 10/8/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/17/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 12/16/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/16/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 12/16/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/22/2026 | Approved | EUGENE CASSIDY |
| Final | 1/22/2026 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 1/22/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/22/2026 | Approved | EUGENE CASSIDY |