1715 1/2-3/4 W 58TH ST 90062

Certificate Information: 1715 1/2-3/4 W 58TH ST 90062

Application / Permit
25014-10000-02666
Plan Check / Job No.
B25LA24096
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE + ADDITION INTO A NEW ADU PER LAMC12.22A.33(c) and(e) TO (E) SFD. ALL WORK PER ENG.
Permit Issued
Issued on 11/20/2025
Issuing Office
Current Status
CofO Issued on 6/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2025 APPLICANT
Assigned to Plan Check Engineer 6/27/2025 LUISANGEL VALENZUELA
Corrections Issued 6/28/2025 LUISANGEL VALENZUELA
Plan Check Approved 11/12/2025 LUISANGEL VALENZUELA
Issued 11/20/2025 APPLICANT
CofO in Progress 6/1/2026 LUIS CASTRO
CofO Issued 6/2/2026 DEROLD HAUFF
Permit Finaled 6/2/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/17/2025 DERRICK MAGEE
Address approval Cleared 8/11/2025 DERRICK MAGEE
Sewer availability Cleared 8/11/2025 DERRICK MAGEE
Community Plan Implem. Overlay Cleared 8/13/2025 MANERI ROMAN
Construction near power lines Cleared 10/2/2025 RIDWAN HARDY
Construction within easement Cleared 10/2/2025 RIDWAN HARDY
Tenant Habitability Plan Cleared 10/20/2025 ARIC DEFUSCO
Eng Process Fee Ord 176,300 Cleared 11/10/2025 DERRICK MAGEE

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: NA55526       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/22/2026 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 2/24/2026 Approved BARRY HACHE
Footing/Foundation/Slab 2/24/2026 Approved BARRY HACHE
PLUMBING-Rough 2/24/2026 Partial Approval BARRY HACHE
ELECTRICAL-Rough 3/12/2026 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 3/12/2026 Partial Approval BARRY HACHE
Green Building Rough 3/12/2026 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 3/18/2026 Corrections Issued BARRY HACHE
PLUMBING-Rough 3/18/2026 Corrections Issued BARRY HACHE
ELECTRICAL-Rough 3/20/2026 Approved RAUL BARAJAS
PLUMBING-Rough 3/20/2026 Partial Inspection RAUL BARAJAS
Underground Mechanical 3/20/2026 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 3/24/2026 Approved BARRY HACHE
Green Building Rough 3/24/2026 Approved BARRY HACHE
Insulation 3/24/2026 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 3/24/2026 Approved BARRY HACHE
Drywall Nailing 3/27/2026 Approved BARRY HACHE
Interior/Exterior Lathing 4/2/2026 Approved BARRY HACHE
Rough-Elec/Plmb/HVAC 4/2/2026 Approved BARRY HACHE
Underground Mechanical 4/8/2026 Approved MICHAEL LEWIS
ELECTRICAL-Final 5/4/2026 Approved LUIS CASTRO
Final 5/4/2026 Corrections Issued LUIS CASTRO
Green Building Final 5/4/2026 Approved LUIS CASTRO
HVAC-Final 5/4/2026 Corrections Issued LUIS CASTRO
PLUMBING-Final 5/4/2026 Corrections Issued LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 5/4/2026 Approved LUIS CASTRO
Final 5/7/2026 Conditional Approval LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 5/7/2026 SGSOV Approved LUIS CASTRO
Final 5/20/2026 Conditional Approval ENRIQUE MIRELES
Final 5/29/2026 OK to Issue CofO LUIS CASTRO
HVAC-Final 5/29/2026 Approved LUIS CASTRO
PLUMBING-Final 5/29/2026 Approved LUIS CASTRO