2931 N TYBURN ST 90039

Certificate Information: 2931 N TYBURN ST 90039

Application / Permit
25014-10000-02653
Plan Check / Job No.
B25LA23991
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel SFD with attached garage, convert attached patio cover to part of the SFD, and new addition at the rear. All work per engineer.
Permit Issued
Issued on 8/27/2025
Issuing Office
Current Status
CofO Issued on 2/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2025 APPLICANT
Assigned to Plan Check Engineer 6/20/2025 NAREG ATARIAN
Corrections Issued 6/21/2025 NAREG ATARIAN
Applicant returned to address corrections 8/12/2025 NAREG ATARIAN
Applicant returned to address corrections 8/14/2025 NAREG ATARIAN
Plan Check Approved 8/19/2025 NAREG ATARIAN
Issued 8/27/2025 APPLICANT
CofO in Progress 2/17/2026 NICHOLAS LOPEZ
Permit Finaled 2/22/2026 DEROLD HAUFF
CofO Issued 2/22/2026 DEROLD HAUFF
Permit Finaled 2/22/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/10/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 7/10/2025 JESSICA OPINION
Sewer availability Cleared 7/10/2025 JESSICA OPINION
ZA Case Cleared 8/5/2025 JASON CHAN
Construction near power lines Cleared 8/15/2025 OSCAR CASTRO
Construction within easement Cleared 8/15/2025 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 375 LA MIRADA AVENUE      SAN MARINO, CA 91108
Engineer Vasquez,, Luis Fernando; Lic. No.: NA56232       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 10/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
FLOOD-Proofing Certificate 10/28/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Approved NICHOLAS LOPEZ
Green Building Rough 10/28/2025 Not Ready for Inspection NICHOLAS LOPEZ
MERV13>=Rough 10/28/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 11/6/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Rough 11/6/2025 Corrections Issued NICHOLAS LOPEZ
ELECTRICAL-Rough 11/7/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 11/7/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 11/13/2025 Approved NICHOLAS LOPEZ
Green Building Rough 11/13/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 11/13/2025 Approved NICHOLAS LOPEZ
Wood Frame 11/13/2025 Conditional Approval NICHOLAS LOPEZ
Green Building Rough 11/25/2025 Not Ready for Inspection NICHOLAS LOPEZ
Insulation 11/25/2025 Approved NICHOLAS LOPEZ
Pre-Inspection 11/26/2025 Partial Inspection NICHOLAS LOPEZ
Interior/Exterior Lathing 12/2/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 12/5/2025 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 2/12/2026 Approved NICHOLAS LOPEZ
Final 2/12/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 2/12/2026 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Rough 2/12/2026 Approved NICHOLAS LOPEZ
MERV13>=Final 2/12/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 2/12/2026 Approved NICHOLAS LOPEZ
Final 2/17/2026 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 2/17/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved NICHOLAS LOPEZ