1219 N BEVERLY ESTATE TER 90210

Certificate Information: 1219 N BEVERLY ESTATE TER 90210

Application / Permit
25014-10000-02645
Plan Check / Job No.
B25LA23922
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) ADDITION AND REMODEL TO EXISTING SFD AND NEW (N) PORCH ADDITION IN FRONT . ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/10/2025
Issuing Office
Current Status
CofO Issued on 1/29/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2025 APPLICANT
Assigned to Plan Check Engineer 6/16/2025 ARAMIK SHAHMIRZAIAN
Corrections Issued 6/17/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 6/23/2025 ARAMIK SHAHMIRZAIAN
Issued 7/10/2025 APPLICANT
CofO in Progress 1/28/2026 CARLOS MATAMOROS
Permit Finaled 1/29/2026 RICHARD STEINBACH
Permit Finaled 1/29/2026 RICHARD STEINBACH
CofO Issued 1/29/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/18/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/18/2025 SAFA JAVANMARDI

Contact Information

Architect Guerrero,, Matthew David; Lic. No.: NA40191       ,
Contractor T N T Building Corporation; Lic. No.: 888520-B       ,
Contractor T N T Simmonds; Lic. No.: 888520-B       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351
Engineer Garcia,, Francisco Diaz; Lic. No.: NA88029       ,

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/15/2025 Approved SEAN HAUPT
Footing/Foundation/Slab 7/15/2025 Approved SEAN HAUPT
PLUMBING-Rough 7/23/2025 Partial Approval SEAN HAUPT
Wood Frame 7/23/2025 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/5/2025 Approved SEAN HAUPT
PLUMBING-Rough 9/8/2025 Approved SEAN HAUPT
ELECTRICAL-Rough 9/10/2025 Partial Approval SEAN HAUPT
HVAC-Rough 9/10/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/23/2025 Approved SEAN HAUPT
Shower Pan 9/23/2025 Approved SEAN HAUPT
Insulation 10/3/2025 Approved SEAN HAUPT
Drywall Nailing 10/9/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 10/9/2025 Approved SEAN HAUPT
Special/Order Compliance 10/9/2025 Partial Approval GEM DE OCAMPO
ELECTRICAL-Final 1/20/2026 Corrections Issued CARLOS MATAMOROS
Final 1/20/2026 Corrections Issued CARLOS MATAMOROS
Gas Test 1/20/2026 Corrections Issued CARLOS MATAMOROS
HVAC-Final 1/20/2026 Approved CARLOS MATAMOROS
PLUMBING-Final 1/20/2026 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/20/2026 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 1/20/2026 Approved CARLOS MATAMOROS
ELECTRICAL-Final 1/22/2026 Approved CARLOS MATAMOROS
Final 1/22/2026 Partial Approval CARLOS MATAMOROS
Gas Test 1/22/2026 Approved CARLOS MATAMOROS
Final 1/28/2026 OK to Issue CofO CARLOS MATAMOROS