872-874 W 6TH ST 90731

Certificate Information: 872-874 W 6TH ST 90731

Application / Permit
25014-10000-02643
Plan Check / Job No.
B25LA23890
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Convert underfloor area to ADU per GC 66323(a)(1) and storage room; add new storage room and recreation room with 1/2 bath. Add bathroom and roof deck on the main floor.
Permit Issued
Issued on 12/2/2025
Issuing Office
Current Status
Issued on 12/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/10/2025 APPLICANT
Assigned to Plan Check Engineer 6/12/2025 SAM CHANG
Corrections Issued 6/27/2025 SAM CHANG
Quality Review Completed 6/30/2025 EUGENE BARBEAU
Applicant returned to address corrections 9/23/2025 SAM CHANG
Plan Check Approved 10/9/2025 SAM CHANG
Issued 12/2/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/27/2025 SAM CHANG
Address approval Cleared 7/21/2025 ERIK BEASLEY
Sewer availability Cleared 7/21/2025 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/28/2025 ERIK BEASLEY

Contact Information

Architect Puskar,, Heidi M; Lic. No.: NA28223       ,
Contractor 808 Builders Inc; Lic. No.: 1091039-B       ,
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 16905 ARMDORE AVE      BELLFLOWER, CA 90706

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2026 Conditional Approval JOSEPH MCGARRY
Wood Frame 3/20/2026 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 7/1/2026 Corrections Issued DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 7/1/2026 Corrections Issued DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 7/1/2026 Not Ready for Inspection DANIEL GONZALEZ
HVAC-Rough 7/1/2026 Corrections Issued DANIEL GONZALEZ
PLUMBING-Rough 7/1/2026 Partial Inspection DANIEL GONZALEZ
Wood Frame 7/1/2026 Corrections Issued DANIEL GONZALEZ
ELECTRICAL-Rough 7/7/2026 Partial Approval DANIEL GONZALEZ
HVAC-Rough 7/7/2026 Partial Approval DANIEL GONZALEZ
Insulation 7/7/2026 Partial Approval DANIEL GONZALEZ
Wood Frame 7/7/2026 Partial Approval DANIEL GONZALEZ
Drywall Nailing 7/16/2026 Partial Approval DANIEL GONZALEZ
Interior/Exterior Lathing 7/16/2026 Partial Approval DANIEL GONZALEZ