1723 S GENESEE AVE 90019

Certificate Information: 1723 S GENESEE AVE 90019

Application / Permit
25014-10000-02636
Plan Check / Job No.
B25LA23854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) Detached garage into an Accessory Dwelling Unit with addition per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 11/12/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2025 APPLICANT
Assigned to Plan Check Engineer 6/11/2025 ALFREDO JARA
Corrections Issued 6/12/2025 ALFREDO JARA
Applicant returned to address corrections 8/1/2025 ALFREDO JARA
Applicant returned to address corrections 9/25/2025 AMY GUEVARRA
Plan Check Approved 9/29/2025 AMY GUEVARRA
Issued 11/12/2025 APPLICANT
CofO in Progress 4/25/2026 WILLIAM SIERRA
No Progress 4/26/2026 DEROLD HAUFF
CofO in Progress 4/26/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/25/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 7/28/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/29/2025 WALLIE JONG
Sewer availability Cleared 7/29/2025 WALLIE JONG
Construction near power lines Cleared 9/22/2025 RIDWAN HARDY
Construction within easement Cleared 9/22/2025 RIDWAN HARDY

Contact Information

Contractor Garcia R Electric; Lic. No.: 967477-B       ,
Contractor R Garcia Electric; Lic. No.: 967477-B       ,
Engineer Azaren,, Neil; Lic. No.: C89881 3400 COTTAGE WAY, STE G2 #26023      SACRAMENTO, CA 95825

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2025 Partial Approval WILLIAM SIERRA
Underground Mechanical 12/2/2025 Partial Approval WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 12/5/2025 Approved BRENDAN MORELLI
Footing/Foundation/Slab 12/5/2025 Approved BRENDAN MORELLI
METHANE-Barrier 12/5/2025 Approved BRENDAN MORELLI
METHANE-Subgrade 12/5/2025 Approved BRENDAN MORELLI
Sewer 12/10/2025 Approved BARRY HACHE
Underground Mechanical 12/10/2025 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 1/20/2026 Conditional Approval BRENDAN MORELLI
HVAC-Rough 1/20/2026 Approved BRENDAN MORELLI
Interior/Exterior Lathing 1/20/2026 Conditional Approval BRENDAN MORELLI
PLUMBING-Rough 1/20/2026 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 1/28/2026 Approved BRENDAN MORELLI
ELECTRICAL-Rough 1/28/2026 Approved BRENDAN MORELLI
METHANE-Rough 1/28/2026 Approved BRENDAN MORELLI
Wood Frame 1/28/2026 Approved BRENDAN MORELLI
Insulation 1/30/2026 Approved ALEX COLIN
Interior/Exterior Lathing 1/30/2026 Not Ready for Inspection ALEX COLIN
Shower Pan 1/30/2026 Approved ALEX COLIN
Drywall Nailing 2/3/2026 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/3/2026 Approved BRENDAN MORELLI
ELECTRICAL-Final 4/15/2026 Corrections Issued BRENDAN MORELLI
Final 4/15/2026 Corrections Issued BRENDAN MORELLI
HVAC-Final 4/15/2026 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 4/15/2026 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV No Gas BRENDAN MORELLI
Smoke Detectors 4/15/2026 Approved BRENDAN MORELLI
ELECTRICAL-Final 4/24/2026 Approved WILLIAM SIERRA
Final 4/24/2026 OK to Issue CofO WILLIAM SIERRA
HVAC-Final 4/24/2026 Approved WILLIAM SIERRA
PLUMBING-Final 4/24/2026 Approved WILLIAM SIERRA