1723 S GENESEE AVE 90019
Certificate Information: 1723 S GENESEE AVE 90019
- Application / Permit
- 25014-10000-02636
- Plan Check / Job No.
- B25LA23854
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert (E) Detached garage into an Accessory Dwelling Unit with addition per LAMC 12.22 A.33(b)(1)
- Permit Issued
- Issued on 11/12/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2025 | ALFREDO JARA |
| Corrections Issued | 6/12/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 8/1/2025 | ALFREDO JARA |
| Applicant returned to address corrections | 9/25/2025 | AMY GUEVARRA |
| Plan Check Approved | 9/29/2025 | AMY GUEVARRA |
| Issued | 11/12/2025 | APPLICANT |
| CofO in Progress | 4/25/2026 | WILLIAM SIERRA |
| No Progress | 4/26/2026 | DEROLD HAUFF |
| CofO in Progress | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 7/28/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2025 | WALLIE JONG |
| Sewer availability | Cleared | 7/29/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 9/22/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/22/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Garcia R Electric; Lic. No.: 967477-B | , |
| Contractor | R Garcia Electric; Lic. No.: 967477-B | , |
| Engineer | Azaren,, Neil; Lic. No.: C89881 | 3400 COTTAGE WAY, STE G2 #26023 SACRAMENTO, CA 95825 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/2/2025 | Partial Approval | WILLIAM SIERRA |
| Underground Mechanical | 12/2/2025 | Partial Approval | WILLIAM SIERRA |
| Excavation/Setback/Form/Re-Bar | 12/5/2025 | Approved | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/5/2025 | Approved | BRENDAN MORELLI |
| METHANE-Barrier | 12/5/2025 | Approved | BRENDAN MORELLI |
| METHANE-Subgrade | 12/5/2025 | Approved | BRENDAN MORELLI |
| Sewer | 12/10/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 12/10/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/20/2026 | Conditional Approval | BRENDAN MORELLI |
| HVAC-Rough | 1/20/2026 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/20/2026 | Conditional Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 1/20/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/28/2026 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Rough | 1/28/2026 | Approved | BRENDAN MORELLI |
| METHANE-Rough | 1/28/2026 | Approved | BRENDAN MORELLI |
| Wood Frame | 1/28/2026 | Approved | BRENDAN MORELLI |
| Insulation | 1/30/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 1/30/2026 | Not Ready for Inspection | ALEX COLIN |
| Shower Pan | 1/30/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 2/3/2026 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 2/3/2026 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| Final | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 4/15/2026 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV No Gas | BRENDAN MORELLI |
| Smoke Detectors | 4/15/2026 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 4/24/2026 | Approved | WILLIAM SIERRA |
| Final | 4/24/2026 | OK to Issue CofO | WILLIAM SIERRA |
| HVAC-Final | 4/24/2026 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 4/24/2026 | Approved | WILLIAM SIERRA |