2833 S OVERLAND AVE 90064
Certificate Information: 2833 S OVERLAND AVE 90064
- Application / Permit
- 25014-10000-02579
- Plan Check / Job No.
- B25LA23328
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) detached garage with addition to ADU per GCS 66323(a)(2) to incorporate unpermitted recreation room to be part of ADU per GCS 65852.2. Patio addition to ADU.
- Permit Issued
- Issued on 8/13/2025
- Issuing Office
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2025 | MINA HABILI |
| Corrections Issued | 6/10/2025 | MINA HABILI |
| Plan Check Approved | 7/2/2025 | RICARDO RAMIREZ |
| Issued | 8/13/2025 | APPLICANT |
| CofO in Progress | 1/27/2026 | ARAM AVEDISIAN |
| Permit Finaled | 1/27/2026 | RICHARD STEINBACH |
| CofO Issued | 1/27/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/27/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2025 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/26/2025 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 7/1/2025 | LANNY MERRICK |
Contact Information
| Contractor | Landmark Builders Trg Inc; Lic. No.: 565610-B | , |
| Contractor | Landmark Builders; Lic. No.: 565610-B | , |
| Engineer | Garcia,, Lionel J; Lic. No.: NA4653 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/11/2025 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 9/16/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 9/23/2025 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 9/25/2025 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 10/6/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/16/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 10/16/2025 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/28/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 10/28/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 10/28/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/3/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 11/3/2025 | Approved | KIRK SANDERS |
| Insulation | 11/3/2025 | Approved | KIRK SANDERS |
| MERV13>=Rough | 11/3/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/10/2025 | Approved | KIRK SANDERS |
| Drywall Nailing | 11/10/2025 | Approved | KIRK SANDERS |
| Shower Pan | 11/10/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 11/17/2025 | Approved | KIRK SANDERS |
| Final | 1/14/2026 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 1/14/2026 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 1/14/2026 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/14/2026 | SGSOV No Gas | ARAM AVEDISIAN |
| Smoke Detectors | 1/14/2026 | Approved | ARAM AVEDISIAN |
| Final | 1/26/2026 | OK to Issue CofO | ARAM AVEDISIAN |
| PLUMBING-Final | 1/26/2026 | Approved | ARAM AVEDISIAN |