212 N AVENUE 49 90042

Certificate Information: 212 N AVENUE 49 90042

Application / Permit
25014-10000-02571
Plan Check / Job No.
B25LA23251
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION 1170 SF AND REMODEL TO EXISTING SFD
Permit Issued
Issued on 10/8/2025
Issuing Office
Current Status
Issued on 10/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 YILE TIAN
Corrections Issued 6/18/2025 YILE TIAN
Quality Review Completed 6/23/2025 KESETE HAREGOT
Building Plans Picked Up 6/25/2025 APPLICANT
Applicant returned to address corrections 8/4/2025 YILE TIAN
Plan Check Approved 9/15/2025 YILE TIAN
Issued 10/8/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/14/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 7/14/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 7/16/2025 MICHAEL TEMPLE
GPI Written Notices Cleared 9/15/2025 YILE TIAN

Contact Information

Contractor Odonnell W Construction; Lic. No.: 1071282-B 1815 FAIR PARK AVENUE      LOS ANGELES, CA 90045
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

BUILDING-Rough-Frame 6/15/2026   
Green Building Rough 6/15/2026   
PLUMBING-Rough 6/15/2026   
HVAC-Rough 6/15/2026   
ELECTRICAL-Rough 6/15/2026   

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/20/2025 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/18/2026 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 5/18/2026 Corrections Issued BRENDAN MORELLI
Green Building Rough 5/18/2026 Not Ready for Inspection BRENDAN MORELLI
HVAC-Rough 5/18/2026 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 5/18/2026 Corrections Issued BRENDAN MORELLI