8327 N CANTERBURY AVE 91352

Certificate Information: 8327 N CANTERBURY AVE 91352

Application / Permit
25014-10000-02559
Plan Check / Job No.
B25LA23078
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE CONVERSION TO (N) ADU WITH ADDITION PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
Permit Issued
Issued on 9/17/2025
Issuing Office
Metro
Current Status
Issued on 9/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 ZAW HAN
Corrections Issued 6/10/2025 ZAW HAN
Building Plans Picked Up 6/16/2025 APPLICANT
Plan Check Approved 9/11/2025 FERNANDO FLORES
Issued 9/17/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/12/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 8/12/2025 DAVID LOPEZ
Construction near power lines Cleared 9/2/2025 GEVORK KARAPETYAN
Construction within easement Cleared 9/2/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 9/10/2025 DAVID LOPEZ
Sewer availability Cleared 9/10/2025 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Wood Frame 7/24/2026   

Inspection Request History

Deputy Drilled-In Anchors 9/29/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 10/2/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 10/2/2025 Corrections Issued VINCENT HANLEY
Wood Frame 10/2/2025 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 10/9/2025 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 10/9/2025 Corrections Issued VINCENT HANLEY
Green Building Rough 10/9/2025 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 1/15/2026 Not Ready for Inspection VINCENT HANLEY
Gas Test 1/15/2026 Approved VINCENT HANLEY
PLUMBING-Rough 1/15/2026 Not Ready for Inspection VINCENT HANLEY
Sewer 1/15/2026 Approved VINCENT HANLEY
PLUMBING-Rough 5/15/2026 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/8/2026 Approved OGANES TARAKHCHYAN