10823 N ALDEA AVE 91344
Certificate Information: 10823 N ALDEA AVE 91344
- Application / Permit
- 25014-10000-02527
- Plan Check / Job No.
- B25LA22852
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- BUILD ADDITION TO EXISTING SFD. ADDITION WILL INCLUDE NEW BEDROOM, NEW BATHROOM, AND NEW CLOSET.
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | ZAW HAN |
| Corrections Issued | 6/10/2025 | ZAW HAN |
| Building Plans Picked Up | 6/11/2025 | APPLICANT |
| Applicant returned to address corrections | 7/3/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 7/7/2025 | NEHEMIAS RAMOS |
| Issued | 7/11/2025 | APPLICANT |
| CofO in Progress | 12/5/2025 | HENRY KIM |
| Permit Finaled | 12/9/2025 | MICHAEL PELHAM |
| CofO Issued | 12/9/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/9/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/26/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2025 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 7/7/2025 | NAZILA NOORIFAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Farag,, Amgad N; Lic. No.: C74076 | 27050 MAPLE TREE CT VALENCIA, CA 91381 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 8/25/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/25/2025 | Partial Approval | STEVEN BACK |
| Pre-Inspection | 8/25/2025 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2025 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/10/2025 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 9/10/2025 | Approved | JEFFREY PARD |
| Green Building Rough | 9/10/2025 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Rough | 9/10/2025 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 9/10/2025 | Approved | JEFFREY PARD |
| Drywall Nailing | 9/16/2025 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 9/16/2025 | No Access for Inspection | JEFFREY PARD |
| Shower Pan | 9/16/2025 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 9/25/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 9/25/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | JEFFREY PARD |
| Green Building Rough | 9/29/2025 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 10/3/2025 | Partial Approval | HENRY KIM |
| Insulation | 10/6/2025 | Corrections Issued | STEVEN BACK |
| Insulation | 10/8/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 10/15/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 10/21/2025 | Approved | STEVEN BACK |
| Pre-Inspection | 11/5/2025 | Partial Inspection | STEVEN BACK |
| Final | 11/19/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/19/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 11/19/2025 | Not Ready for Inspection | STEVEN BACK |
| Final | 12/5/2025 | OK to Issue CofO | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 12/5/2025 | SGSOV Gas Company | HENRY KIM |
| Smoke Detectors | 12/5/2025 | Approved | HENRY KIM |