2133 W BRANDEN ST 90026

Certificate Information: 2133 W BRANDEN ST 90026

Application / Permit
25014-10000-02518
Plan Check / Job No.
B25LA22749
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: 1-story addition and remodel to existing S.F.D.
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2025 APPLICANT
Assigned to Plan Check Engineer 6/4/2025 CAROLEAN BASMA
Corrections Issued 6/5/2025 CAROLEAN BASMA
Plan Check Approved 6/28/2025 CAROLEAN BASMA
Issued 7/14/2025 APPLICANT
CofO in Progress 5/26/2026 HAMIK HARTOUNIAN
Permit Finaled 5/28/2026 DEROLD HAUFF
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/9/2025 JONATHAN HOM
Roof/Waste drainage to street Cleared 6/13/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/23/2025 WALLIE JONG

Contact Information

Contractor Rodo Development Inc; Lic. No.: 1100805-B       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403
Engineer Shahbaz,, Shant Pierre; Lic. No.: NA93079       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/15/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Approved HAMIK HARTOUNIAN
Underground Mechanical 11/6/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/17/2025 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 11/17/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 11/19/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 11/24/2025 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 11/24/2025 Corrections Issued ALIZAH MAYAGOITIA
MERV13>=Rough 11/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 11/24/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/26/2025 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 12/1/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 12/1/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/1/2025 Partial Approval HAMIK HARTOUNIAN
MERV13>=Rough 12/1/2025 Approved HAMIK HARTOUNIAN
Insulation 12/3/2025 Approved ALEX COLIN
Drywall Nailing 12/8/2025 Approved GEM DE OCAMPO
Final 3/2/2026 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 3/2/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 3/2/2026 Approved HAMIK HARTOUNIAN
Final 3/11/2026 Partial Inspection HAMIK HARTOUNIAN
Final 5/26/2026 OK to Issue CofO HAMIK HARTOUNIAN