1332 S BURNSIDE AVE 90019

Certificate Information: 1332 S BURNSIDE AVE 90019

Application / Permit
25014-10000-02507
Plan Check / Job No.
B25LA22623
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Convert (E) Detached Garage with Addition to Accessory Dwelling Unit Per GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g)
Permit Issued
Issued on 7/31/2025
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 RAHEL BEYENE
Corrections Issued 6/10/2025 RAHEL BEYENE
Quality Review Completed 6/20/2025 HERNAN ARREOLA
Applicant returned to address corrections 7/18/2025 RAHEL BEYENE
Applicant returned to address corrections 7/22/2025 RAHEL BEYENE
Plan Check Approved 7/30/2025 RAHEL BEYENE
Issued 7/31/2025 APPLICANT
CofO in Progress 2/19/2026 BRENDAN MORELLI
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/11/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 6/11/2025 DERRICK MAGEE
Sewer availability Cleared 6/11/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 6/12/2025 DERRICK MAGEE
Construction near power lines Cleared 7/15/2025 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Irene; Lic. No.: NA68382       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/20/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 9/11/2025 Partial Approval ARTHUR NEGRETE
METHANE-Barrier 9/11/2025 Approved ARTHUR NEGRETE
METHANE-Subgrade 9/11/2025 Approved ARTHUR NEGRETE
Underground Mechanical 9/19/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 9/25/2025 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 9/25/2025 Approved ARTHUR NEGRETE
Grounding or Bonding 9/25/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 10/7/2025 Partial Approval ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Approved ARTHUR NEGRETE
HVAC-Rough 10/7/2025 Not Ready for Inspection ARTHUR NEGRETE
METHANE-Rough 10/7/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 10/7/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 10/21/2025 Approved WILLIAM SIERRA
ELECTRICAL-Rough 10/21/2025 Approved WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Approved WILLIAM SIERRA
HVAC-Rough 10/21/2025 Approved WILLIAM SIERRA
Service/Power Release 11/4/2025 Approved WILLIAM SIERRA
Insulation 11/6/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 11/12/2025 Approved GEM DE OCAMPO
Drywall Nailing 11/13/2025 Approved GEM DE OCAMPO
Gas Test 1/22/2026 Approved BRENDAN MORELLI
HVAC-Final 1/22/2026 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Final 1/22/2026 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 2/5/2026 Corrections Issued BRENDAN MORELLI
Final 2/5/2026 Corrections Issued BRENDAN MORELLI
HVAC-Final 2/5/2026 Approved BRENDAN MORELLI
PLUMBING-Final 2/5/2026 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 2/5/2026 Approved BRENDAN MORELLI
ELECTRICAL-Final 2/10/2026 Not Ready for Inspection BRENDAN MORELLI
Final 2/10/2026 Corrections Issued BRENDAN MORELLI
Final 2/18/2026 OK to Issue CofO BRENDAN MORELLI