8483 N GLENCREST DR 91352

Certificate Information: 8483 N GLENCREST DR 91352

Application / Permit
25014-10000-02505
Plan Check / Job No.
B25LA22612
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND 1 STORY ADDITION TO (E) SFD WITH ATTACHED GARAGE
Permit Issued
Issued on 7/9/2025
Issuing Office
Current Status
CofO Issued on 6/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 CARLOS MONTES
Corrections Issued 6/5/2025 CARLOS MONTES
Building Plans Picked Up 6/12/2025 APPLICANT
Plan Check Approved 6/26/2025 EDWIN MARTINEZ
Issued 7/9/2025 APPLICANT
CofO in Progress 4/3/2026 DAVID ANDERSON
CofO Issued 6/9/2026 RUBEN SALAS
Permit Finaled 6/9/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/10/2025 CINDY QI
Grading Pre-Inspection Cleared 6/10/2025 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 6/11/2025 CINDY QI

Contact Information

Contractor Myriad Inc; Lic. No.: 1103257-B 9908 RANCHO CABALLO DR      SUNLAND, CA 91040
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/12/2025 Partial Approval DAVID ANDERSON
Green Building Rough 9/12/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 9/12/2025 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval DAVID ANDERSON
Insulation 9/16/2025 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 10/30/2025 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 10/30/2025 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Partial Approval DAVID ANDERSON
Green Building Rough 10/30/2025 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 11/20/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/8/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 12/8/2025 Approved DAVID ANDERSON
Green Building Rough 12/8/2025 Approved DAVID ANDERSON
HVAC-Rough 12/8/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/8/2025 Partial Approval DAVID ANDERSON
Insulation 12/22/2025 Corrections Issued MICHAEL CORTEZ
Shower Pan 12/22/2025 Corrections Issued MICHAEL CORTEZ
Insulation 12/29/2025 Approved MICHAEL CORTEZ
Shower Pan 12/29/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/31/2025 Approved DAVID ANDERSON
Drywall Nailing 1/6/2026 Approved DAVID MATSON
Shower Pan 1/21/2026 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/23/2026 Approved DAVID ANDERSON
Final 3/13/2026 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 3/13/2026 Approved DAVID ANDERSON
Green Building Final 3/13/2026 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Approved DAVID ANDERSON
Smoke Detectors 3/13/2026 Approved DAVID ANDERSON
Final 3/31/2026 OK to Issue CofO DAVID ANDERSON