3137 E FAIRMOUNT ST 90063

Certificate Information: 3137 E FAIRMOUNT ST 90063

Application / Permit
25014-10000-02495
Plan Check / Job No.
B25LA22568
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 8/6/2025
Issuing Office
Metro
Current Status
Issued on 8/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 AUNG SOE
Corrections Issued 6/9/2025 AUNG SOE
Building Plans Picked Up 6/13/2025 APPLICANT
Plan Check Approved 7/30/2025 DANIEL YIP
Issued 8/6/2025 APPLICANT

Permit Application Clearance Information

Clean Up Green Up Cleared 7/7/2025 DORIAN AGUILAR
Eng Process Fee Ord 176,300 Cleared 7/10/2025 RYAN CASTRO
Sewer availability Cleared 7/10/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 7/21/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 7/30/2025 AUNG SOE

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/16/2025 Conditional Approval GEM DE OCAMPO
Excavation/Setback/Form/Re-Bar 12/17/2025 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/17/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 2/6/2026 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 2/20/2026 Not Ready for Inspection RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 2/20/2026 Partial Approval RONNIE MEDINA
BUILDING-Rough-Frame 2/24/2026 Not Ready for Inspection DAVID WILLIAMS
Deputy Wood Construction 2/24/2026 Conditional Approval GEM DE OCAMPO
Floor/Roof Diaphrgm/Shear Wall 2/24/2026 Approved DAVID WILLIAMS
Green Building Rough 2/24/2026 Not Ready for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 4/15/2026 Approved ALIZAH MAYAGOITIA
HVAC-Rough 4/15/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 4/15/2026 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/13/2026 Approved OSVALDO PARAMO
Green Building Rough 5/13/2026 Approved OSVALDO PARAMO
HVAC-Rough 5/13/2026 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/13/2026 Partial Approval OSVALDO PARAMO
Interior/Exterior Lathing 5/14/2026 Partial Approval OSVALDO PARAMO
Insulation 5/18/2026 Corrections Issued ALEX COLIN
Drywall Nailing 5/21/2026 Approved OSVALDO PARAMO
Insulation 5/21/2026 Approved OSVALDO PARAMO