20933 S HALLDALE AVE 90501
Certificate Information: 20933 S HALLDALE AVE 90501
- Application / Permit
- 25014-10000-02493
- Plan Check / Job No.
- B25LA22563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF EXISTING GARAGE WITH ADDITION TO DETACHED ADU PER LAMC 12.22 A.33(b)(1) (1-STORY)
- Permit Issued
- Issued on 8/18/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/5/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 6/5/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 8/16/2025 | CARLOS MONTES |
| Issued | 8/18/2025 | APPLICANT |
| CofO in Progress | 6/5/2026 | EUGENE CASSIDY |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 7/8/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | CELINA MORENO |
| Sewer availability | Cleared | 7/15/2025 | RYAN CASTRO |
Contact Information
| Contractor | Ortiz Building; Lic. No.: 1076126-B | , |
| Engineer | Hassan,, Mohamed Ali; Lic. No.: NA5285 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/1/2025 | Partial Approval | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 10/8/2025 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/8/2025 | Approved | EUGENE CASSIDY |
| Sewer | 10/15/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/12/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/12/2025 | Approved | EUGENE CASSIDY |
| Gas Test | 11/12/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 11/12/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 11/12/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | EUGENE CASSIDY |
| PLUMBING-Rough | 11/12/2025 | Approved | EUGENE CASSIDY |
| Insulation | 11/17/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/21/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/25/2025 | Approved | EUGENE CASSIDY |
| Shower Pan | 11/25/2025 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 12/4/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/26/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 1/26/2026 | Corrections Issued | EUGENE CASSIDY |
| Gas Test | 1/26/2026 | Approved | EUGENE CASSIDY |
| Green Building Final | 1/26/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 1/26/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 1/26/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 1/26/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/5/2026 | Approved | EUGENE CASSIDY |
| Final | 2/5/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/5/2026 | Approved | EUGENE CASSIDY |
| HVAC-Final | 2/5/2026 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 2/5/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/5/2026 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/5/2026 | Approved | EUGENE CASSIDY |
| Final | 6/5/2026 | OK to Issue CofO | EUGENE CASSIDY |