20933 S HALLDALE AVE 90501

Certificate Information: 20933 S HALLDALE AVE 90501

Application / Permit
25014-10000-02493
Plan Check / Job No.
B25LA22563
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING GARAGE WITH ADDITION TO DETACHED ADU PER LAMC 12.22 A.33(b)(1) (1-STORY)
Permit Issued
Issued on 8/18/2025
Issuing Office
Current Status
CofO in Progress on 6/5/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/4/2025 NEHEMIAS RAMOS
Corrections Issued 6/5/2025 NEHEMIAS RAMOS
Plan Check Approved 8/16/2025 CARLOS MONTES
Issued 8/18/2025 APPLICANT
CofO in Progress 6/5/2026 EUGENE CASSIDY

Permit Application Clearance Information

Address approval Cleared 7/8/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 7/8/2025 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/9/2025 CELINA MORENO
Sewer availability Cleared 7/15/2025 RYAN CASTRO

Contact Information

Contractor Ortiz Building; Lic. No.: 1076126-B       ,
Engineer Hassan,, Mohamed Ali; Lic. No.: NA5285       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/1/2025 Partial Approval EUGENE CASSIDY
Deputy Drilled-In Anchors 10/8/2025 Approved EUGENE CASSIDY
Footing/Foundation/Slab 10/8/2025 Approved EUGENE CASSIDY
Sewer 10/15/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/4/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/12/2025 Approved EUGENE CASSIDY
ELECTRICAL-Rough 11/12/2025 Approved EUGENE CASSIDY
Gas Test 11/12/2025 Approved EUGENE CASSIDY
Green Building Rough 11/12/2025 Approved EUGENE CASSIDY
HVAC-Rough 11/12/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/12/2025 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 11/12/2025 Approved EUGENE CASSIDY
Insulation 11/17/2025 Approved EUGENE CASSIDY
Drywall Nailing 11/21/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/25/2025 Approved EUGENE CASSIDY
Shower Pan 11/25/2025 Approved EUGENE CASSIDY
Underground Mechanical 12/4/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 1/26/2026 Not Ready for Inspection EUGENE CASSIDY
Final 1/26/2026 Corrections Issued EUGENE CASSIDY
Gas Test 1/26/2026 Approved EUGENE CASSIDY
Green Building Final 1/26/2026 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 1/26/2026 Approved EUGENE CASSIDY
PLUMBING-Final 1/26/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/26/2026 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 1/26/2026 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 2/5/2026 Approved EUGENE CASSIDY
Final 2/5/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 2/5/2026 Approved EUGENE CASSIDY
HVAC-Final 2/5/2026 Approved EUGENE CASSIDY
PLUMBING-Final 2/5/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/5/2026 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/5/2026 Approved EUGENE CASSIDY
Final 6/5/2026 OK to Issue CofO EUGENE CASSIDY