1318 W 51ST PL 90037
Certificate Information: 1318 W 51ST PL 90037
- Application / Permit
- 25014-10000-02485
- Plan Check / Job No.
- B25LA22522
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE AND STORAGE BLDG. INTO A.D.U.PER STATE LAW (GCS 66323(a)(1)) WITH ENTRY AND PORCH ADDITION
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Current Status
- CofO Issued on 12/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/7/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 6/11/2025 | APPLICANT |
| Plan Check Approved | 6/13/2025 | AUNG SOE |
| Issued | 6/18/2025 | APPLICANT |
| CofO in Progress | 12/18/2025 | BARRY HACHE |
| Permit Finaled | 12/19/2025 | DEROLD HAUFF |
| CofO Issued | 12/19/2025 | DEROLD HAUFF |
| Permit Finaled | 12/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 6/6/2025 | MANERI ROMAN |
| Address approval | Cleared | 6/10/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | ABEL CASILLAS |
| Roof/Waste drainage to street | Cleared | 6/10/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 6/10/2025 | ABEL CASILLAS |
Contact Information
| Contractor | Arrow Construction Co; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | PO BOX 40237 DOWNEY, CA 90239 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/28/2025 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 8/28/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 9/26/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 9/26/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/30/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 9/30/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/2/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 10/2/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 10/6/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 10/6/2025 | Approved | BARRY HACHE |
| Green Building Rough | 10/6/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 10/6/2025 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 10/8/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/16/2025 | Approved | ALEX COLIN |
| Insulation | 10/16/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/20/2025 | Not Ready for Inspection | ALEX COLIN |
| Interior/Exterior Lathing | 10/20/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 10/21/2025 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 10/21/2025 | Corrections Issued | BARRY HACHE |
| Drywall Nailing | 10/22/2025 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 10/22/2025 | Approved | BARRY HACHE |
| Underground Mechanical | 10/30/2025 | Corrections Issued | BARRY HACHE |
| Final | 12/11/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 12/11/2025 | No Access for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 12/15/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 12/15/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 12/16/2025 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 12/16/2025 | Approved | BARRY HACHE |
| Green Building Final | 12/16/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 12/16/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 12/16/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Not Required | BARRY HACHE |
| Smoke Detectors | 12/16/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 12/17/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 12/18/2025 | OK to Issue CofO | BARRY HACHE |
| Green Building Final | 12/18/2025 | Approved | BARRY HACHE |
| Service/Power Release | 12/18/2025 | Approved | BARRY HACHE |
| Smoke Detectors | 12/18/2025 | Approved | BARRY HACHE |