5618 E BUCHANAN ST 90042

Certificate Information: 5618 E BUCHANAN ST 90042

Application / Permit
25014-10000-02469
Plan Check / Job No.
B25LA22408
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan - ground floor addition to (E) 1-story detached garage resulting in 1-story detached ADU & garage per GC 66323(a)(2) R3/U occupancy
Permit Issued
Issued on 9/9/2025
Issuing Office
Current Status
Issued on 9/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2025 APPLICANT
Assigned to Plan Check Engineer 6/9/2025 KELVIN CHUONG
Corrections Issued 6/10/2025 KELVIN CHUONG
Applicant returned to address corrections 7/15/2025 KELVIN CHUONG
Applicant returned to address corrections 7/22/2025 KELVIN CHUONG
Applicant returned to address corrections 7/25/2025 KELVIN CHUONG
Applicant returned to address corrections 8/28/2025 KELVIN CHUONG
Plan Check Approved 8/30/2025 KELVIN CHUONG
Issued 9/9/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/14/2025 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/14/2025 LEE GUILBEAUX
Grading Pre-Inspection Cleared 6/23/2025 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 6/28/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 7/22/2025 LEE GUILBEAUX
Sewer availability Cleared 7/22/2025 LEE GUILBEAUX
City Hist. Cultural Monument Cleared 8/25/2025 NATHALY DE LA PAZ
HPOZ Cleared 8/25/2025 NATHALY DE LA PAZ
GPI Written Notices Cleared 8/30/2025 KELVIN CHUONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/5/2026 Not Ready for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 2/5/2026 Not Ready for Inspection DAVID WILLIAMS
Pre-Inspection 2/5/2026 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 2/9/2026 Approved DAVID WILLIAMS
PLUMBING-Rough 2/18/2026 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 2/23/2026 Approved DAVID WILLIAMS
Footing/Foundation/Slab 2/23/2026 Approved DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 3/5/2026 Partial Approval DAVID WILLIAMS
Interior/Exterior Lathing 3/9/2026 Partial Approval GEM DE OCAMPO
Deputy Wood Construction 3/10/2026 Conditional Approval GEM DE OCAMPO
Floor/Roof Diaphrgm/Shear Wall 3/10/2026 Partial Approval DAVID WILLIAMS
Deputy Wood Construction 3/20/2026 Conditional Approval RONNIE MEDINA
Floor/Roof Diaphrgm/Shear Wall 3/20/2026 Approved GEM DE OCAMPO
ELECTRICAL-Rough 5/1/2026 Approved DAVID WILLIAMS
HVAC-Rough 5/1/2026 Corrections Issued DAVID WILLIAMS
PLUMBING-Rough 5/1/2026 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 5/18/2026 Approved NICHOLAS LOPEZ
Green Building Rough 5/18/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Rough 5/18/2026 Not Ready for Inspection NICHOLAS LOPEZ
Sewer 5/18/2026 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 5/27/2026 Approved NICHOLAS LOPEZ
Green Building Rough 5/27/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 5/27/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/27/2026 Partial Approval NICHOLAS LOPEZ
Insulation 6/5/2026 Corrections Issued GEM DE OCAMPO