237-237 1/2 E 65TH ST 90003

Certificate Information: 237-237 1/2 E 65TH ST 90003

Application / Permit
25014-10000-02468
Plan Check / Job No.
B25LA22405
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT EXISTING SFD INTO A NEW DUPLEX WITH NEW ADDITION (PER WFPP DESIGN)
Permit Issued
Issued on 7/31/2025
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 MAHNAZ NOURHASHEMI
Assigned to Zoning Architect 6/5/2025 MEGAN KOLP
Corrections Issued 6/10/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 6/10/2025 KEN GILL
Building Plans Picked Up 6/12/2025 APPLICANT
Plan Check Approved 7/30/2025 MAHNAZ NOURHASHEMI
Issued 7/31/2025 APPLICANT
CofO in Progress 12/29/2025 JOHN QUINTANILLA
Permit Finaled 12/30/2025 DEROLD HAUFF
CofO Issued 12/30/2025 DEROLD HAUFF
Permit Finaled 12/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/17/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 6/17/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 6/17/2025 DAVID LOPEZ
Sewer availability Cleared 6/17/2025 DAVID LOPEZ
Community Plan Implem. Overlay Cleared 7/9/2025 ANACANY HURTADO
Miscellaneous Cleared 7/9/2025 ANACANY HURTADO
Zoning Plan Check Cleared 7/16/2025 MEGAN KOLP

Contact Information

Contractor Southland Building & Remodel Company; Lic. No.: 894311-B 1324 WEST ROSECRANS AVENUE      COMPTON, CA 90222
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 8/11/2025 Approved JOHN QUINTANILLA
Underground Mechanical 9/2/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Approved ALEX COLIN
Insulation 9/4/2025 Partial Approval ALEX COLIN
ELECTRICAL-Rough 9/23/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 9/23/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 9/23/2025 Not Ready for Inspection JOHN QUINTANILLA
Sewer 9/23/2025 Approved JOHN QUINTANILLA
Rough-Elec/Plmb/HVAC 9/25/2025 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 9/25/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 9/26/2025 Approved JOHN QUINTANILLA
Rough-Elec/Plmb/HVAC 9/26/2025 Approved JOHN QUINTANILLA
Insulation 9/30/2025 Approved RONNIE MEDINA
Interior/Exterior Lathing 9/30/2025 Approved RONNIE MEDINA
Insulation 10/1/2025 Partial Approval JOHN QUINTANILLA
Drywall Nailing 10/3/2025 Approved RONNIE MEDINA
ELECTRICAL-Final 12/5/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 12/5/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Final 12/8/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 12/8/2025 Approved LUIS CASTRO
HVAC-Final 12/8/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 12/8/2025 Approved LUIS CASTRO
PLUMBING-Final 12/8/2025 Approved LUIS CASTRO
PLUMBING-Rough 12/8/2025 Approved LUIS CASTRO
Smoke Detectors 12/8/2025 Approved LUIS CASTRO
Verify Rec and Parks Fee Memo 12/8/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 12/11/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 12/11/2025 Approved JOHN QUINTANILLA
Final 12/11/2025 Corrections Issued JOHN QUINTANILLA
Gas Test 12/11/2025 Approved JOHN QUINTANILLA
Green Building Final 12/11/2025 Approved JOHN QUINTANILLA
Green Building Rough 12/11/2025 Approved JOHN QUINTANILLA
HVAC-Final 12/11/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 12/11/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 12/11/2025 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 12/11/2025 Approved JOHN QUINTANILLA
Final 12/18/2025 Corrections Issued JOHN QUINTANILLA
Final 12/24/2025 OK to Issue CofO JOHN QUINTANILLA