2298 W 74TH ST 90043
Certificate Information: 2298 W 74TH ST 90043
- Application / Permit
- 25014-10000-02454
- Plan Check / Job No.
- B25LA22246
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. PROPOSED ONE STORY ACCESSORY DWELLING UNIT GARAGE CONVERSION AND ADDITION PER LAMC 12.22 A33(c) & (e).
- Permit Issued
- Issued on 8/25/2025
- Issuing Office
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2025 | FERNANDO FLORES |
| Corrections Issued | 6/3/2025 | FERNANDO FLORES |
| Plan Check Approved | 8/11/2025 | FERNANDO FLORES |
| Issued | 8/25/2025 | APPLICANT |
| CofO in Progress | 5/21/2026 | SALVADOR MARTINEZ |
| CofO Issued | 5/22/2026 | DEROLD HAUFF |
| Permit Finaled | 5/22/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 6/12/2025 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2025 | CELINA MORENO |
| Sewer availability | Cleared | 6/13/2025 | CELINA MORENO |
| Construction near power lines | Cleared | 7/31/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Southerland,, Richard Charles; Lic. No.: C88965 | 2335 E COLORADO BLVD SUITE 115, # 170 PASADENA, CA 91107 |
| Engineer | Southerland,, Richard Charles; Lic. No.: NA88965 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 9/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/29/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/1/2025 | Partial Approval | SALVADOR MARTINEZ |
| Sewer | 10/1/2025 | Approved | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 10/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 10/21/2025 | Conditional Approval | ANTHONY RAMOS |
| Footing/Foundation/Slab | 11/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/26/2025 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 11/26/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/2/2026 | Not Ready for Inspection | ANTHONY RAMOS |
| ELECTRICAL-Rough | 1/2/2026 | Approved | ANTHONY RAMOS |
| Green Building Rough | 1/2/2026 | Not Ready for Inspection | ANTHONY RAMOS |
| PLUMBING-Rough | 1/2/2026 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 1/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 1/27/2026 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/6/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 2/6/2026 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 2/20/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/20/2026 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/27/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/27/2026 | Partial Approval | SALVADOR MARTINEZ |
| Underground Mechanical | 2/27/2026 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 3/5/2026 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 3/9/2026 | Approved | SALVADOR MARTINEZ |
| Gas Test | 4/8/2026 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 4/8/2026 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/30/2026 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 4/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 4/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 4/30/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 4/30/2026 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 4/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/30/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Smoke Detectors | 4/30/2026 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/7/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Final | 5/18/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 5/18/2026 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 5/21/2026 | OK to Issue CofO | SALVADOR MARTINEZ |