1123-1123 1/2 E 106TH ST 90002
Certificate Information: 1123-1123 1/2 E 106TH ST 90002
- Application / Permit
- 25014-10000-02436
- Plan Check / Job No.
- B25LA22063
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Conversion and addition to existing S.F.D. to create new attached A.D.U. per LAMC 12.22 A 33 (c) and (e). Remodel existing S.F.D. to create new bathroom. Design per WFPP.
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Current Status
- CofO Issued on 3/25/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2025 | CAROLEAN BASMA |
| Corrections Issued | 6/3/2025 | CAROLEAN BASMA |
| Plan Check Approved | 6/16/2025 | CAROLEAN BASMA |
| Issued | 6/23/2025 | APPLICANT |
| CofO in Progress | 2/4/2026 | ARTHUR NEGRETE |
| Permit Finaled | 3/25/2026 | ANSON MAGLASANG |
| CofO Issued | 3/25/2026 | ANSON MAGLASANG |
| Permit Finaled | 3/25/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/12/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | JEREMY CHOK |
| Roof/Waste drainage to street | Cleared | 6/12/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 6/12/2025 | JEREMY CHOK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2025 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/22/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 8/14/2025 | Corrections Issued | ANTHONY EGSON |
| Sewer | 8/14/2025 | Partial Approval | ANTHONY EGSON |
| Insulation | 8/18/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/27/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/2/2025 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/8/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2025 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 9/8/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Interior/Exterior Lathing | 9/11/2025 | Conditional Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 9/22/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 9/22/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/9/2025 | Approved | ANTHONY EGSON |
| Insulation | 10/10/2025 | Partial Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/15/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 10/15/2025 | Approved | ANTHONY EGSON |
| Insulation | 10/17/2025 | Corrections Issued | ANTHONY EGSON |
| Insulation | 10/22/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/28/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 10/31/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/26/2026 | Approved | ARTHUR NEGRETE |
| Final | 1/26/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 1/26/2026 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 1/26/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 1/26/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 1/26/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/3/2026 | OK to Issue CofO | ARTHUR NEGRETE |