3128 S HADDINGTON DR 90064
Certificate Information: 3128 S HADDINGTON DR 90064
- Application / Permit
- 25014-10000-02434
- Plan Check / Job No.
- B25LA22061
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN ADDITION AND INTERIOR REMODEL TO (E) SFD.
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Current Status
- CofO Issued on 7/18/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | VARAND SARKISIAN |
| Corrections Issued | 6/9/2025 | VARAND SARKISIAN |
| Quality Review Completed | 6/13/2025 | GARO TELMI |
| Plan Check Approved | 7/9/2025 | VARAND SARKISIAN |
| Issued | 7/11/2025 | APPLICANT |
| CofO in Progress | 7/16/2026 | ASHLEY THOMPSON |
| Permit Finaled | 7/18/2026 | RICHARD STEINBACH |
| CofO Issued | 7/18/2026 | RICHARD STEINBACH |
| Permit Finaled | 7/18/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZI | Cleared | 6/17/2025 | KYLE WINSTON |
| Sewer availability | Cleared | 6/20/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2025 | LIAM ODONOVAN |
| Grading Pre-Inspection | Cleared | 6/25/2025 | MICHAEL TEMPLE |
| Roof/Waste drainage to street | Cleared | 6/26/2025 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: NA69673 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/4/2025 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 8/7/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 8/26/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 8/26/2025 | Conditional Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 8/27/2025 | Conditional Approval | ASHLEY THOMPSON |
| Deputy Steel/Welding | 8/27/2025 | Conditional Approval | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 8/29/2025 | Approved | ASHLEY THOMPSON |
| Structural Steel Frame | 8/29/2025 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 9/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 9/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/9/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Rough | 9/11/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 9/11/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/16/2025 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 9/16/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/16/2025 | Approved | BOBBY KEY |
| Shower Pan | 9/16/2025 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 9/19/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 9/19/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| MERV13>=Rough | 9/19/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Deputy Wood Construction | 9/22/2025 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/24/2025 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 9/24/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| MERV13>=Rough | 9/24/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/29/2025 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/29/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/1/2025 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 10/1/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 10/1/2025 | Partial Approval | ASHLEY THOMPSON |
| Insulation | 10/3/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 10/3/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 10/8/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| Final | 5/14/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Final | 5/14/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 5/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| MERV13>=Final | 5/14/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 5/14/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 5/14/2026 | SGSOV Not Ready | ASHLEY THOMPSON |
| Smoke Detectors | 5/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/11/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Final | 6/11/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 6/11/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 6/11/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 6/11/2026 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 6/11/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/7/2026 | Approved | MORRIS JACKSON |
| Final | 7/7/2026 | Corrections Issued | MORRIS JACKSON |
| HVAC-Final | 7/7/2026 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 7/7/2026 | Approved | MORRIS JACKSON |
| Smoke Detectors | 7/7/2026 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 7/15/2026 | Approved | ASHLEY THOMPSON |
| Final | 7/15/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| HVAC-Final | 7/15/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/15/2026 | Approved | ASHLEY THOMPSON |