1023 N WATSON AVE 90744
Certificate Information: 1023 N WATSON AVE 90744
- Application / Permit
- 25014-10000-02411
- Plan Check / Job No.
- B25LA21954
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO ADU & REROOF (244 SF). ADDITION (301 S.F.) TOTAL 545 S.F. 1 BEDROOM, 1 BATHROOM, KITCHEN AND DINING. LAUNDRY CLOSET
- Permit Issued
- Issued on 12/10/2025
- Issuing Office
- Current Status
- Issued on 12/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2025 | TSE MING HUANG |
| Corrections Issued | 6/7/2025 | TSE MING HUANG |
| Plan Check Approved | 11/26/2025 | TSE MING HUANG |
| Issued | 12/10/2025 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/8/2025 | JACQUELINE TORRES |
| Clean Up Green Up | Cleared | 7/8/2025 | JACQUELINE TORRES |
| Address approval | Cleared | 7/11/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 7/11/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 9/5/2025 | SAFA JAVANMARDI |
| Abandoned oil well | Cleared | 10/20/2025 | PATRICK PEREZ |
| Oil Wells | Cleared | 11/21/2025 | EDBER MACEDO |
Contact Information
| Architect | Lockyer,, Susan M; Lic. No.: C25683 | 232 BON VUE CT. APPLEGATE, CA 95703 |
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2026 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 2/24/2026 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/27/2026 | Partial Approval | EUGENE CASSIDY |
| METHANE-Subgrade | 3/2/2026 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/4/2026 | Approved | EUGENE CASSIDY |
| METHANE-Barrier | 3/4/2026 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 3/4/2026 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 3/17/2026 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 3/17/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 3/17/2026 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 3/24/2026 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 3/25/2026 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Rough | 3/26/2026 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 3/26/2026 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 3/26/2026 | Partial Approval | JOSEPH MCGARRY |