6461 W 82ND ST 90045
Certificate Information: 6461 W 82ND ST 90045
- Application / Permit
- 25014-10000-02365
- Plan Check / Job No.
- B25LA21558
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER GCS 66323(a)(2).
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Current Status
- CofO Issued on 5/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 6/2/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 6/10/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 6/16/2025 | GIOVANNY CHAVEZ |
| Issued | 7/11/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | MORRIS JACKSON |
| Permit Finaled | 5/23/2026 | RICHARD STEINBACH |
| CofO Issued | 5/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 6/7/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2025 | DARIN LAM |
| Sewer availability | Cleared | 6/9/2025 | DARIN LAM |
| Specific Plan | Cleared | 6/11/2025 | RICHARD WOO |
Contact Information
| Contractor | Ivory Home Builders Inc; Lic. No.: 1135067-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Underground Mechanical | 8/14/2025 | Approved | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 8/19/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 10/22/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 10/22/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Green Building Rough | 10/22/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 10/22/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Rough | 10/22/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 10/30/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Rough | 10/30/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 10/30/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 10/30/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 10/30/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/13/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 11/13/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 11/13/2025 | Partial Approval | RUBEN RIVAS |
| Insulation | 12/2/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 12/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 12/16/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/24/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/14/2026 | Approved | DAKOTA LOW |
| Shower Pan | 1/14/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 1/21/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/30/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/30/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 4/30/2026 | Approved | ANTHONY EGSON |
| Green Building Final | 4/30/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 4/30/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 4/30/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 4/30/2026 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 4/30/2026 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 4/30/2026 | Approved | ANTHONY EGSON |
| Final | 5/12/2026 | Not Ready for Inspection | DAVID FEILER |
| Service/Power Release | 5/12/2026 | Not Required | DAVID FEILER |
| Final | 5/20/2026 | OK to Issue CofO | MORRIS JACKSON |