5308 S CIMARRON ST 90062
Certificate Information: 5308 S CIMARRON ST 90062
- Application / Permit
- 25014-10000-02352
- Plan Check / Job No.
- B25LA21482
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan 1 story detached ADU addition and covertion of (e) 2 car garage per GC 66323(a)(2) to storage per WFPP
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2025 | MARCELA FRANQUEZ |
| Corrections Issued | 6/24/2025 | MARCELA FRANQUEZ |
| Quality Review Completed | 7/2/2025 | HERNAN ARREOLA |
| Building Plans Picked Up | 7/7/2025 | APPLICANT |
| Plan Check Approved | 9/30/2025 | MARCELA FRANQUEZ |
| Issued | 9/30/2025 | APPLICANT |
| CofO in Progress | 4/22/2026 | ENRIQUE MIRELES |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
| CofO Issued | 4/26/2026 | DEROLD HAUFF |
| Permit Finaled | 4/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/16/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/16/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/16/2025 | DAVID LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/17/2025 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 12/17/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 12/29/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 1/23/2026 | Approved | BARRY HACHE |
| HVAC-Rough | 1/23/2026 | Approved | BARRY HACHE |
| PLUMBING-Rough | 1/23/2026 | Corrections Issued | BARRY HACHE |
| Gas Test | 1/26/2026 | Partial Approval | BARRY HACHE |
| PLUMBING-Rough | 1/26/2026 | Approved | BARRY HACHE |
| Wood Frame | 1/26/2026 | Not Ready for Inspection | BARRY HACHE |
| BUILDING-Rough-Frame | 2/4/2026 | Corrections Issued | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Not Ready for Inspection | BARRY HACHE |
| Green Building Rough | 2/4/2026 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 2/4/2026 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2026 | Approved | BARRY HACHE |
| Insulation | 2/6/2026 | Approved | BARRY HACHE |
| Drywall Nailing | 2/24/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/24/2026 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 4/2/2026 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 4/2/2026 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 4/2/2026 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Not Ready | BARRY HACHE |
| ELECTRICAL-Final | 4/9/2026 | Corrections Issued | JOSH MEISTER |
| PLUMBING-Final | 4/9/2026 | Corrections Issued | JOSH MEISTER |
| Final | 4/10/2026 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 4/10/2026 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/10/2026 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/17/2026 | OK to Issue CofO | ENRIQUE MIRELES |