8049 S DUNFIELD AVE 90045
Certificate Information: 8049 S DUNFIELD AVE 90045
- Application / Permit
- 25014-10000-02336
- Plan Check / Job No.
- B25LA21322
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Remodel and addition to existing single family residence
- Permit Issued
- Issued on 7/3/2025
- Issuing Office
- Current Status
- CofO in Progress on 6/4/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | ADAM HEGAZI |
| Corrections Issued | 5/28/2025 | ADAM HEGAZI |
| Plan Check Approved | 7/2/2025 | ADAM HEGAZI |
| Issued | 7/3/2025 | APPLICANT |
| CofO in Progress | 6/4/2026 | MORRIS JACKSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 6/2/2025 | LIAM ODONOVAN |
Contact Information
| Architect | Williams,, Mark Irwin; Lic. No.: C28727 | 18809 ROSELLE AVENUE TORRANCE, CA 90504 |
| Contractor | Owner-Builder | , |
| Engineer | Bartelle,, Kristofer Grimm; Lic. No.: C84617 | 22910 BURBANK BLVD WOODLAND HILLS, CA 91367 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/1/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 8/26/2025 | Not Ready for Inspection | RUBEN RIVAS |
| PLUMBING-Rough | 8/26/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/12/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 11/12/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 11/12/2025 | Not Ready for Inspection | RUBEN RIVAS |
| HVAC-Rough | 11/12/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 11/12/2025 | Approved | RUBEN RIVAS |
| Insulation | 12/8/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/8/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/15/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/15/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 12/31/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/15/2026 | Approved | MICHAEL ALLEN |
| Final | 4/15/2026 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 4/15/2026 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 4/15/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 4/15/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 4/15/2026 | Approved | MICHAEL ALLEN |
| Final | 6/3/2026 | OK to Issue CofO | MORRIS JACKSON |
| Green Building Final | 6/3/2026 | Approved | MORRIS JACKSON |