5421 N BUSHNELL WAY 90042
Certificate Information: 5421 N BUSHNELL WAY 90042
- Application / Permit
- 25014-10000-02304
- Plan Check / Job No.
- B25LA21104
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan CONVERSION OF (E) 365SF DETACHED GARAGE TO ADU PER GC 66323(A)(1)
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- Current Status
- CofO Issued on 4/5/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 5/29/2025 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 6/21/2025 | NGHI SU |
| Applicant returned to address corrections | 7/3/2025 | NEHEMIAS RAMOS |
| Plan Check Approved | 7/15/2025 | NGHI SU |
| Issued | 7/15/2025 | APPLICANT |
| CofO in Progress | 4/3/2026 | LILIANA PORTILLO |
| Permit Finaled | 4/5/2026 | DEROLD HAUFF |
| Permit Finaled | 4/5/2026 | DEROLD HAUFF |
| CofO Issued | 4/5/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 6/4/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2025 | MICHAEL BROWN |
| Grading Pre-Inspection | Cleared | 6/22/2025 | NEHEMIAS RAMOS |
Contact Information
| Contractor | Vaisman Construction Inc; Lic. No.: 1076712-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/26/2025 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 9/30/2025 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/9/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 11/4/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 11/5/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| MERV13>=Rough | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Wood Frame | 11/21/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/25/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/25/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/25/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 11/25/2025 | Approved | LILIANA PORTILLO |
| Insulation | 12/2/2025 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/3/2025 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 12/8/2025 | Conditional Approval | GEM DE OCAMPO |
| Drywall Nailing | 1/27/2026 | Approved | LILIANA PORTILLO |
| Insulation | 1/27/2026 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/27/2026 | Approved | LILIANA PORTILLO |
| Shower Pan | 1/27/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/1/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 4/1/2026 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 4/1/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 4/1/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/2/2026 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/2/2026 | Approved | LILIANA PORTILLO |
| Final | 4/2/2026 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 4/2/2026 | Approved | LILIANA PORTILLO |
| Green Building Rough | 4/2/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/2/2026 | Approved | LILIANA PORTILLO |
| MERV13>=Final | 4/2/2026 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 4/2/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/2/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/2/2026 | SGSOV No Gas | LILIANA PORTILLO |
| Smoke Detectors | 4/2/2026 | Approved | LILIANA PORTILLO |