17511-17513 W BULLOCK ST 91316

Certificate Information: 17511-17513 W BULLOCK ST 91316

Application / Permit
25014-10000-02284
Plan Check / Job No.
B25LA20941
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) 196 SF ATTACHED GARAGE AND 129 SF ADDITION TO (N) 325 SF ATTACHED ADU PER LAMC12.22A.33(c) and(e), ALL WORK PER ENG. AND INTERIOR REMODEL TO (E) SFD TO CREATE A NEW LAUNDRY ROOM
Permit Issued
Issued on 9/26/2025
Issuing Office
Current Status
CofO Issued on 4/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2025 APPLICANT
Assigned to Plan Check Engineer 5/23/2025 LUISANGEL VALENZUELA
Corrections Issued 5/24/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 6/24/2025 LUISANGEL VALENZUELA
Plan Check Approved 7/14/2025 LUISANGEL VALENZUELA
Issued 9/26/2025 APPLICANT
CofO in Progress 1/7/2026 MORRIS JACKSON
Permit Finaled 4/9/2026 JOHN JANSON
CofO Issued 4/9/2026 JOHN JANSON
Permit Finaled 4/9/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/6/2025 BIAINA HARITUNIAN
Watercourse Cleared 6/6/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/10/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/10/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/20/2025 BIAINA HARITUNIAN

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B       ,
Engineer Adams,, Robert Charles; Lic. No.: NA21234       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/6/2025 Partial Approval GEVORK IPCHYAN
Deputy Drilled-In Anchors 10/8/2025 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 10/8/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 10/8/2025 Approved MORRIS JACKSON
PLUMBING-Rough 10/8/2025 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 10/23/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Partial Approval MORRIS JACKSON
HVAC-Rough 10/23/2025 Approved MORRIS JACKSON
PLUMBING-Rough 10/23/2025 Approved MORRIS JACKSON
Insulation 10/28/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/28/2025 Approved MORRIS JACKSON
Shower Pan 10/28/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 10/31/2025 Approved MORRIS JACKSON
Green Building Rough 10/31/2025 Approved MORRIS JACKSON
Drywall Nailing 11/4/2025 Approved MORRIS JACKSON
Gas Test 11/4/2025 Corrections Issued MORRIS JACKSON
Sewer 11/4/2025 Approved MORRIS JACKSON
Final 12/12/2025 Corrections Issued MORRIS JACKSON
Gas Test 12/12/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Approved MORRIS JACKSON
Service/Power Release 12/12/2025 Partial Inspection MORRIS JACKSON
Smoke Detectors 12/12/2025 Approved MORRIS JACKSON
Final 12/16/2025 OK to Issue CofO MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 12/16/2025 SGSOV Approved MORRIS JACKSON