17511-17513 W BULLOCK ST 91316
Certificate Information: 17511-17513 W BULLOCK ST 91316
- Application / Permit
- 25014-10000-02284
- Plan Check / Job No.
- B25LA20941
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) 196 SF ATTACHED GARAGE AND 129 SF ADDITION TO (N) 325 SF ATTACHED ADU PER LAMC12.22A.33(c) and(e), ALL WORK PER ENG. AND INTERIOR REMODEL TO (E) SFD TO CREATE A NEW LAUNDRY ROOM
- Permit Issued
- Issued on 9/26/2025
- Issuing Office
- Current Status
- CofO Issued on 4/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/24/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/24/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/14/2025 | LUISANGEL VALENZUELA |
| Issued | 9/26/2025 | APPLICANT |
| CofO in Progress | 1/7/2026 | MORRIS JACKSON |
| Permit Finaled | 4/9/2026 | JOHN JANSON |
| CofO Issued | 4/9/2026 | JOHN JANSON |
| Permit Finaled | 4/9/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2025 | BIAINA HARITUNIAN |
| Watercourse | Cleared | 6/6/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/10/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/20/2025 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | , |
| Engineer | Adams,, Robert Charles; Lic. No.: NA21234 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/6/2025 | Partial Approval | GEVORK IPCHYAN |
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Corrections Issued | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/8/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 10/8/2025 | Partial Approval | MORRIS JACKSON |
| ELECTRICAL-Rough | 10/23/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Partial Approval | MORRIS JACKSON |
| HVAC-Rough | 10/23/2025 | Approved | MORRIS JACKSON |
| PLUMBING-Rough | 10/23/2025 | Approved | MORRIS JACKSON |
| Insulation | 10/28/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 10/28/2025 | Approved | MORRIS JACKSON |
| Shower Pan | 10/28/2025 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Corrections Issued | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/31/2025 | Approved | MORRIS JACKSON |
| Green Building Rough | 10/31/2025 | Approved | MORRIS JACKSON |
| Drywall Nailing | 11/4/2025 | Approved | MORRIS JACKSON |
| Gas Test | 11/4/2025 | Corrections Issued | MORRIS JACKSON |
| Sewer | 11/4/2025 | Approved | MORRIS JACKSON |
| Final | 12/12/2025 | Corrections Issued | MORRIS JACKSON |
| Gas Test | 12/12/2025 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 12/12/2025 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 12/12/2025 | Partial Inspection | MORRIS JACKSON |
| Smoke Detectors | 12/12/2025 | Approved | MORRIS JACKSON |
| Final | 12/16/2025 | OK to Issue CofO | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | MORRIS JACKSON |