12705 N COMETA AVE 91340
Certificate Information: 12705 N COMETA AVE 91340
- Application / Permit
- 25014-10000-02272
- Plan Check / Job No.
- B25VN10652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF (E) ONE STORY DETACHED GARAGE INTO AN ADU PER GC & 66323(a)(1)
- Permit Issued
- Issued on 11/2/2025
- Issuing Office
- Current Status
- Issued on 11/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2025 | SERGIO GUTIERREZ |
| Corrections Issued | 5/20/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/29/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 9/9/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/10/2025 | SERGIO GUTIERREZ |
| Issued | 11/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2025 | LEE GUILBEAUX |
| Permit | Cleared | 7/12/2025 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/12/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/12/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/14/2025 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 8/11/2025 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/17/2025 | Partial Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/23/2025 | Approved | KEVIN BERBERYAN |
| Sewer | 12/23/2025 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 1/23/2026 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 4/7/2026 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/7/2026 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/27/2026 | Approved Pending GreenApproval | KEVIN BERBERYAN |
| Green Building Rough | 4/27/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/27/2026 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 4/27/2026 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 4/27/2026 | Approved | KEVIN BERBERYAN |
| Insulation | 5/11/2026 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 5/11/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Shower Pan | 5/11/2026 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/21/2026 | Corrections Issued | KEVIN BERBERYAN |
| Drywall Nailing | 5/26/2026 | Approved | KEVIN BERBERYAN |