1739 S OGDEN DR 90019
Certificate Information: 1739 S OGDEN DR 90019
- Application / Permit
- 25014-10000-02260
- Plan Check / Job No.
- B25LA20675
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL (E) SFD INCLUDING RESTROOM AND KITCHEN REMODEL, ADDING SKYLIGHTS, ADDITION NEW MUDROOM/LAUNDRY ROOM, CONVERT (E) COVERED SIDE ENTRANCE TO LIVABLE SPACE, NEW TRELLIS
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Metro
- Current Status
- Issued on 6/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2025 | CRISTINA SALAZAR |
| Corrections Issued | 5/20/2025 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/10/2025 | CRISTINA SALAZAR |
| Plan Check Approved | 6/18/2025 | MINA HABILI |
| Issued | 6/18/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 5/20/2025 | JEANIE LAM |
Contact Information
| Contractor | Rebuilt Homes Inc; Lic. No.: 1063540-B | 2201 N LAKEWOOD BLVD STE D643 LONG BEACH, CA 90815 |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: C64738 | 16111 PRAIRIE AVE APT. 117 LAWNDALE, CA 90260 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 8/8/2025 | Approved | ARTHUR NEGRETE |
| METHANE-Rough | 8/8/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 8/8/2025 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 9/3/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 9/4/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 9/5/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 9/15/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/15/2025 | Approved | ALEX COLIN |
| Final | 2/25/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/25/2026 | Approved | BRENDAN MORELLI |
| Green Building Final | 2/25/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| METHANE-Barrier | 2/25/2026 | Approved | BRENDAN MORELLI |
| METHANE-Subgrade | 2/25/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 2/25/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 3/11/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Final | 3/11/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 3/11/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 3/16/2026 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 3/16/2026 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 3/16/2026 | Approved | BRENDAN MORELLI |
| Final | 3/20/2026 | Corrections Issued | WILLIAM SIERRA |
| Final | 3/26/2026 | Conditional Approval | JOSH MEISTER |