2321 W 74TH ST 90043
Certificate Information: 2321 W 74TH ST 90043
- Application / Permit
- 25014-10000-02232
- Plan Check / Job No.
- B25LA20387
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TO CONVERT PORTION OF THE (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT WITH ADDITION PER LAMC 12.22A.33(b)(1). ADDITION TO THE (E) DETACHED GARAGE.
- Permit Issued
- Issued on 7/31/2025
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 5/24/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 7/19/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 7/30/2025 | GIOVANNY CHAVEZ |
| Issued | 7/31/2025 | APPLICANT |
| CofO in Progress | 4/2/2026 | MICHAEL LEWIS |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
| CofO Issued | 4/2/2026 | DEROLD HAUFF |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/6/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/11/2025 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 7/2/2025 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kashe,, Andrew; Lic. No.: NA94117 | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/15/2025 | Corrections Issued | BARRY HACHE |
| Sewer | 9/15/2025 | Approved | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 9/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 9/30/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 10/2/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 10/2/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Special/Order Compliance | 11/4/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/19/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 11/19/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/12/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Underground Mechanical | 12/12/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 12/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/18/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 12/18/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 12/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/24/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/24/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 12/31/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 12/31/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 1/6/2026 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 1/6/2026 | Approved | SALVADOR MARTINEZ |
| Insulation | 1/8/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 1/12/2026 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 1/12/2026 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 1/16/2026 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/21/2026 | No Access for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/26/2026 | Approved | GEM DE OCAMPO |
| Final | 3/5/2026 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 3/5/2026 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/5/2026 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 3/5/2026 | Approved | SABAS ALONSO |
| Final | 3/26/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 3/26/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 3/26/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Service/Power Release | 3/31/2026 | Approved | MICHAEL LEWIS |
| Final | 4/2/2026 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 4/2/2026 | Approved | MICHAEL LEWIS |