101 N WOODBURN DR 90049

Certificate Information: 101 N WOODBURN DR 90049

Application / Permit
25014-10000-02230
Plan Check / Job No.
B25LA20379
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. New 2 story addition, new addition to existing kitchen and new 2 car garage. Conversion of existing 2 car garage to interior of SFD.
Permit Issued
Issued on 8/26/2025
Issuing Office
Current Status
Issued on 8/26/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 JESSE VIDUYA
Corrections Issued 6/16/2025 JESSE VIDUYA
Quality Review Completed 6/24/2025 CHAD DOI
Applicant returned to address corrections 7/24/2025 JESSE VIDUYA
Plan Check Approved 8/13/2025 JESSE VIDUYA
Plan Check Approved 8/26/2025 JESSE VIDUYA
Issued 8/26/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/7/2025 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 7/9/2025 HISASHI KOBAYAKAWA
Sewer availability Cleared 7/9/2025 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 7/25/2025 JERRY KAO
Private street Cleared 7/28/2025 MATHEW QUAN
ZA Case Cleared 7/28/2025 MATHEW QUAN
ZA Case Cleared 7/28/2025 MATHEW QUAN
ZA Case Cleared 7/28/2025 MATHEW QUAN
GPI Written Notices Cleared 8/13/2025 JESSE VIDUYA
Grading Pre-Inspection Cleared 8/13/2025 JESSE VIDUYA
Public Works-Highway Ded. Cleared 5/23/2026 CHRISTINE REUSCH
Public Works-Open Permits Cleared 5/23/2026 CHRISTINE REUSCH
Public Works-Sewers Cleared 5/23/2026 CHRISTINE REUSCH

Contact Information

Contractor Owner-Builder       ,
Engineer Youm,, Moung Han; Lic. No.: C74086 309 S BERENDO ST APT 6      LOS ANGELES, CA 90020

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/28/2026 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 7/8/2026 Approved EVAN COOPER
BUILDING-Rough-Frame 7/22/2026 Partial Approval EVAN COOPER
PLUMBING-Rough 7/22/2026 Partial Approval EVAN COOPER
Underground Mechanical 7/22/2026 Partial Approval EVAN COOPER