10724 W STAGG ST 91352
Certificate Information: 10724 W STAGG ST 91352
- Application / Permit
- 25014-10000-02223
- Plan Check / Job No.
- B25LA20294
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) COVERED PATIO AND PROPOSE ADDITION TO EXISTING SINGLE FAMILY DWELLING. FIRE SPRINKLER SYSTEM THROUGHOUT
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Valley
- Current Status
- Issued on 6/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2025 | CARLOS MONTES |
| Corrections Issued | 5/22/2025 | CARLOS MONTES |
| Building Plans Picked Up | 5/23/2025 | APPLICANT |
| Plan Check Approved | 6/18/2025 | MINA HABILI |
| Issued | 6/20/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/30/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 6/2/2025 | SAFA JAVANMARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2025 | Partial Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 7/8/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/11/2025 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 7/14/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/14/2025 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/6/2025 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/6/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/6/2025 | Partial Approval | MATTHEW NELSON |
| Insulation | 8/11/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/29/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Rough | 8/29/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 8/29/2025 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/10/2025 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/24/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 10/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 10/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 10/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 10/24/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 11/3/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 11/3/2025 | Approved | MATTHEW NELSON |
| Insulation | 11/7/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/5/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/5/2025 | Partial Approval | MATTHEW NELSON |
| Drywall Nailing | 12/15/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 12/31/2025 | Approved | NICHOLAS TROWBRIDGE |