11901 W PACIFIC AVE 90066

Certificate Information: 11901 W PACIFIC AVE 90066

Application / Permit
25014-10000-02186
Plan Check / Job No.
B25LA19956
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan PROPOSED INTERIOR REMODEL TO EXISTING S.F.R. TWO STORY, ADDITION TO 1st FLOOR 153 SQ. FT, ADDITION TO 2nd FLOOR 795 SQ. FT., AND METAL ROOF.
Permit Issued
Issued on 7/31/2025
Issuing Office
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 YILE TIAN
Corrections Issued 6/26/2025 YILE TIAN
Quality Review Completed 6/30/2025 KESETE HAREGOT
Applicant returned to address corrections 7/28/2025 YILE TIAN
Plan Check Approved 7/30/2025 YILE TIAN
Issued 7/31/2025 APPLICANT
CofO in Progress 2/4/2026 MICHAEL ALLEN
Permit Finaled 2/5/2026 RICHARD STEINBACH
CofO Issued 2/5/2026 RICHARD STEINBACH
Permit Finaled 2/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/5/2025 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 7/9/2025 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 7/11/2025 MICHAEL TEMPLE
GPI Written Notices Cleared 7/29/2025 JOHN FRANCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/15/2025 Conditional Approval JAYLIN GRAVITTE
Footing/Foundation/Slab 8/19/2025 Corrections Issued RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 8/21/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 8/22/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 8/28/2025 Partial Approval JAYLIN GRAVITTE
Insulation 8/28/2025 Partial Approval JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 9/2/2025 Partial Approval WILBER ROSALES
Deputy Steel/Welding 9/10/2025 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/11/2025 Partial Approval WILBER ROSALES
PLUMBING-Rough 10/6/2025 Corrections Issued RUBEN RIVAS
Wood Frame 10/6/2025 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Corrections Issued WILBER ROSALES
Deputy Wood Construction 10/14/2025 Conditional Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 10/23/2025 Approved WILBER ROSALES
Green Building Rough 10/23/2025 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 10/23/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 10/29/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 10/29/2025 Approved WILBER ROSALES
Green Building Rough 10/29/2025 Approved WILBER ROSALES
HVAC-Rough 10/29/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 10/29/2025 Partial Approval WILBER ROSALES
Insulation 10/31/2025 Approved WILBER ROSALES
Drywall Nailing 11/7/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 11/13/2025 Approved JESUS PINEDA
Shower Pan 11/13/2025 Approved JESUS PINEDA
Final 1/28/2026 Corrections Issued ANTHONY EGSON
Green Building Final 1/28/2026 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 1/28/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 2/3/2026 Approved MICHAEL ALLEN
Final 2/3/2026 OK to Issue CofO MICHAEL ALLEN
Green Building Final 2/3/2026 Approved MICHAEL ALLEN
HVAC-Final 2/3/2026 Approved MICHAEL ALLEN
PLUMBING-Final 2/3/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 2/3/2026 Approved MICHAEL ALLEN