4630 N SALOMA AVE 91403
Certificate Information: 4630 N SALOMA AVE 91403
- Application / Permit
- 25014-10000-02167
- Plan Check / Job No.
- B25LA19727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - MAJOR REMODEL AND 1ST AND 2ND FLOOR ADDITION TO EXISTING SFD W GARAGE, SEE COMMENTS
- Permit Issued
- Issued on 8/14/2025
- Issuing Office
- Current Status
- CofO Issued on 6/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | STARR CHEN |
| Corrections Issued | 5/20/2025 | STARR CHEN |
| Quality Review Completed | 5/20/2025 | EUGENE BARBEAU |
| Assigned to Zoning Architect | 5/22/2025 | RYAN DEL POSO |
| Plan Check Approved | 8/8/2025 | STARR CHEN |
| Issued | 8/14/2025 | APPLICANT |
| CofO in Progress | 6/3/2026 | RAUL OLAGI |
| CofO Issued | 6/9/2026 | RUBEN SALAS |
| Permit Finaled | 6/9/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/30/2025 | GILBERT URREA |
| Address approval | Cleared | 6/12/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 6/17/2025 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 6/24/2025 | TREVOR QUAN |
| Zoning Plan Check | Cleared | 7/24/2025 | RYAN DEL POSO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: C92714 | 331 ARDEN AVE SUIT 201 GLENDALE, CA 91203 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2025 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 9/4/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 9/4/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 9/9/2025 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 9/9/2025 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/12/2025 | Approved | JACK KARGODORIAN |
| Deputy Wood Construction | 10/1/2025 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 10/1/2025 | Partial Approval | DAVID ANDERSON |
| Deputy Wood Construction | 10/23/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2025 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 10/23/2025 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/28/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2025 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 10/28/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 11/21/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 11/24/2025 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/2/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 12/2/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/3/2025 | Not Ready for Inspection | LOUIS ESCOTO |
| Shower Pan | 12/3/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Rough | 12/4/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 12/8/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/12/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/16/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 12/16/2025 | Approved | JACK KARGODORIAN |
| Insulation | 12/18/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/18/2025 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 1/9/2026 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 5/13/2026 | Approved | MISAEL ESPARZA |
| Final | 5/13/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/13/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 5/13/2026 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 5/13/2026 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/19/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/19/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/19/2026 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 5/19/2026 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 5/19/2026 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/26/2026 | Approved | RAUL OLAGI |
| Final | 5/26/2026 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 5/26/2026 | Approved | RAUL OLAGI |
| HVAC-Final | 5/26/2026 | Approved | RAUL OLAGI |
| Service/Power Release | 5/26/2026 | Approved | RAUL OLAGI |
| Final | 6/3/2026 | OK to Issue CofO | RAUL OLAGI |