6124 S HARCOURT AVE 90043

Certificate Information: 6124 S HARCOURT AVE 90043

Application / Permit
25014-10000-02162
Plan Check / Job No.
B25LA19684
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AND ADD TO (E) 2-CAR GARAGE TO CREATE A.D.U. PER ORDINANCE AND LAMC 12.22 A33(c)&(d).
Permit Issued
Issued on 8/28/2025
Issuing Office
Current Status
CofO Issued on 5/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2025 APPLICANT
Assigned to Plan Check Engineer 5/19/2025 LAWRENCE QUIRANTE
Corrections Issued 5/21/2025 LAWRENCE QUIRANTE
Building Plans Picked Up 5/23/2025 APPLICANT
Applicant returned to address corrections 6/10/2025 ZAW HAN
Plan Check Approved 6/12/2025 ZAW HAN
Issued 8/28/2025 APPLICANT
CofO in Progress 5/10/2026 SALVADOR MARTINEZ
CofO Issued 5/13/2026 DEROLD HAUFF
Permit Finaled 5/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/31/2025 JESSICA OPINION
Roof/Waste drainage to street Cleared 5/31/2025 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/9/2025 MICHAEL BROWN
Sewer availability Cleared 6/9/2025 MICHAEL BROWN

Contact Information

Contractor Summit Remodeling Group Inc; Lic. No.: 1107646-B 1825 N LAS PALMAS AVE 525      LOS ANGELES, CA 90028
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 10/20/2025 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 10/20/2025 Partial Approval BRENDAN MORELLI
Excavation/Setback/Form/Re-Bar 10/23/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 10/28/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 11/17/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/1/2025 Not Ready for Inspection SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/3/2025 Approved SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/5/2025 Partial Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 12/18/2025 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Rough 12/30/2025 Approved SALVADOR MARTINEZ
Sewer 1/2/2026 Approved ANTHONY RAMOS
Sewer 1/5/2026 Partial Inspection SALVADOR MARTINEZ
Underground Mechanical 1/6/2026 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 1/8/2026 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 1/9/2026 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 1/9/2026 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 1/13/2026 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 1/26/2026 Corrections Issued ENRIQUE MIRELES
Shower Pan 1/26/2026 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 1/28/2026 Partial Approval GEM DE OCAMPO
Shower Pan 1/28/2026 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 1/30/2026 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 1/30/2026 Approved SALVADOR MARTINEZ
Green Building Rough 1/30/2026 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 2/10/2026 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 2/10/2026 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 2/24/2026 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 2/24/2026 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 2/27/2026 Approved MICHAEL LEWIS
Insulation 3/4/2026 Approved MICHAEL LEWIS
Drywall Nailing 3/10/2026 Approved ALEX COLIN
Interior/Exterior Lathing 3/24/2026 Approved LUIS CASTRO
ELECTRICAL-Final 4/21/2026 Approved SALVADOR MARTINEZ
Final 4/21/2026 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 4/21/2026 Approved SALVADOR MARTINEZ
Green Building Final 4/21/2026 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Final 4/21/2026 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 4/21/2026 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 4/21/2026 Approved SALVADOR MARTINEZ
Final 4/27/2026 Corrections Issued SALVADOR MARTINEZ
Green Building Final 4/27/2026 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/27/2026 SGSOV Not Ready SALVADOR MARTINEZ
Final 5/5/2026 Corrections Issued SALVADOR MARTINEZ
Green Building Final 5/5/2026 Approved SALVADOR MARTINEZ
HVAC-Final 5/5/2026 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Approved SALVADOR MARTINEZ
Final 5/8/2026 OK to Issue CofO SALVADOR MARTINEZ
Service/Power Release 5/8/2026 Approved SALVADOR MARTINEZ