4432 S BERRYMAN AVE 90230
Certificate Information: 4432 S BERRYMAN AVE 90230
- Application / Permit
- 25014-10000-02106
- Plan Check / Job No.
- B25LA19122
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN SUPPLEMENTAL permit to 25014-10000-01208 to include Second floor addition on (E) two story SFD. WORK DONE PER ARCHITECTURE DESIGN. **NFPA-13D FIRE SPIRKLERS THROUGHOUT**
- Permit Issued
- Issued on 9/12/2025
- Issuing Office
- Current Status
- Issued on 9/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | KHUONG TRUONG |
| Corrections Issued | 6/13/2025 | GEORGE JOLAKIAN |
| Quality Review Completed | 7/3/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/21/2025 | GEORGE JOLAKIAN |
| Plan Check Approved | 9/12/2025 | KHUONG TRUONG |
| Issued | 9/12/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/28/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2025 | CELINA MORENO |
| Sewer availability | Cleared | 7/9/2025 | CELINA MORENO |
Contact Information
| Architect | Lopez,, Craig Joseph; Lic. No.: NA14263 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 10/28/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 11/26/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 12/19/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 12/19/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 12/19/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 12/19/2025 | Approved | WILBER ROSALES |
| MERV13>=Rough | 12/19/2025 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Rough | 12/19/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 1/8/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 1/8/2026 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 1/8/2026 | Approved | ANTHONY EGSON |
| MERV13>=Rough | 1/8/2026 | Approved | ANTHONY EGSON |
| Insulation | 1/14/2026 | Corrections Issued | RUBEN RIVAS |
| Drywall Nailing | 1/21/2026 | Partial Inspection | DAKOTA LOW |
| BUILDING-Rough-Frame | 2/2/2026 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 2/2/2026 | Approved | RUBEN RIVAS |
| Insulation | 2/2/2026 | Approved | RUBEN RIVAS |
| Drywall Nailing | 2/13/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 2/23/2026 | Approved | DAKOTA LOW |