1645 S MALCOLM AVE 203 90024

Certificate Information: 1645 S MALCOLM AVE 203 90024

Application / Permit
25014-10000-02101
Plan Check / Job No.
B25LA19071
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(35) Condo-Multi Family
Work Description
REMOVE EXISTING NONE BEARING WALL AND WINDOW AND CONVERT/ADD EXISTING BALCONY AREA TO HABITABLE AREA IN UNIT 203 OF 4-STORY, 8 UNIT CONDO
Permit Issued
Issued on 10/8/2025
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 SERGIO GUTIERREZ
Assigned to Zoning Architect 5/15/2025 NEVRIK NAVASARTIAN
Corrections Issued 5/19/2025 SERGIO GUTIERREZ
Quality Review Completed 5/29/2025 PRANITA SHAH
Plan Check Approved 9/9/2025 SERGIO GUTIERREZ
Plan Check Approved 9/30/2025 SERGIO GUTIERREZ
Issued 10/8/2025 APPLICANT
CofO in Progress 12/29/2025 DANIEL VARNUM
Permit Finaled 12/30/2025 DAVID TSAU
CofO Issued 12/30/2025 DAVID TSAU
Permit Finaled 12/30/2025 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/12/2025 RYAN CASTRO
Sewer availability Cleared 6/12/2025 RYAN CASTRO
Specific Plan Cleared 6/13/2025 PEDRO AYALA
"Q" conditions Cleared 6/30/2025 ASHLEY RODARTE
Tract Map conditions Cleared 6/30/2025 ASHLEY RODARTE
Specific Plan Cleared 7/1/2025 JACKSON OLSON
Specific Plan Cleared 7/1/2025 JACKSON OLSON
Tenant Habitability Plan Cleared 7/3/2025 KORNEL LELEA
Fire Marshal Fire Life Safety Cleared 7/24/2025 SERGIO GUTIERREZ
DAS Clearance Cleared 8/14/2025 ELIZABETH TOMS
Zoning Plan Check Cleared 8/21/2025 NEVRIK NAVASARTIAN

Contact Information

Contractor Lmo Builders Inc; Lic. No.: 1062505-B       ,

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 10/17/2025 Not Ready for Inspection DANIEL VARNUM
Wood Frame 10/17/2025 Corrections Issued DANIEL VARNUM
METHANE-Rough 10/30/2025 Approved RICARDO ROBLES
Wood Frame 10/30/2025 Partial Inspection RICARDO ROBLES
Insulation 11/4/2025 Not Ready for Inspection RICARDO ROBLES
Interior/Exterior Lathing 11/4/2025 Approved RICARDO ROBLES
Wood Frame 11/21/2025 Approved DANIEL VARNUM
Drywall Nailing 12/15/2025 Approved DANIEL VARNUM
Final 12/26/2025 Partial Inspection DANIEL VARNUM
Footing/Foundation/Slab 12/26/2025 Approved DANIEL VARNUM
METHANE-Barrier 12/26/2025 Approved DANIEL VARNUM
METHANE-Subgrade 12/26/2025 Approved DANIEL VARNUM
Smoke Detectors 12/26/2025 Approved DANIEL VARNUM
Final 12/30/2025 OK to Issue CofO DANIEL VARNUM