1645 S MALCOLM AVE 203 90024
Certificate Information: 1645 S MALCOLM AVE 203 90024
- Application / Permit
- 25014-10000-02101
- Plan Check / Job No.
- B25LA19071
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- REMOVE EXISTING NONE BEARING WALL AND WINDOW AND CONVERT/ADD EXISTING BALCONY AREA TO HABITABLE AREA IN UNIT 203 OF 4-STORY, 8 UNIT CONDO
- Permit Issued
- Issued on 10/8/2025
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 5/15/2025 | NEVRIK NAVASARTIAN |
| Corrections Issued | 5/19/2025 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/29/2025 | PRANITA SHAH |
| Plan Check Approved | 9/9/2025 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/30/2025 | SERGIO GUTIERREZ |
| Issued | 10/8/2025 | APPLICANT |
| CofO in Progress | 12/29/2025 | DANIEL VARNUM |
| Permit Finaled | 12/30/2025 | DAVID TSAU |
| CofO Issued | 12/30/2025 | DAVID TSAU |
| Permit Finaled | 12/30/2025 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 6/12/2025 | RYAN CASTRO |
| Specific Plan | Cleared | 6/13/2025 | PEDRO AYALA |
| "Q" conditions | Cleared | 6/30/2025 | ASHLEY RODARTE |
| Tract Map conditions | Cleared | 6/30/2025 | ASHLEY RODARTE |
| Specific Plan | Cleared | 7/1/2025 | JACKSON OLSON |
| Specific Plan | Cleared | 7/1/2025 | JACKSON OLSON |
| Tenant Habitability Plan | Cleared | 7/3/2025 | KORNEL LELEA |
| Fire Marshal Fire Life Safety | Cleared | 7/24/2025 | SERGIO GUTIERREZ |
| DAS Clearance | Cleared | 8/14/2025 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 8/21/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Contractor | Lmo Builders Inc; Lic. No.: 1062505-B | , |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 10/17/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 10/17/2025 | Corrections Issued | DANIEL VARNUM |
| METHANE-Rough | 10/30/2025 | Approved | RICARDO ROBLES |
| Wood Frame | 10/30/2025 | Partial Inspection | RICARDO ROBLES |
| Insulation | 11/4/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Interior/Exterior Lathing | 11/4/2025 | Approved | RICARDO ROBLES |
| Wood Frame | 11/21/2025 | Approved | DANIEL VARNUM |
| Drywall Nailing | 12/15/2025 | Approved | DANIEL VARNUM |
| Final | 12/26/2025 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 12/26/2025 | Approved | DANIEL VARNUM |
| METHANE-Barrier | 12/26/2025 | Approved | DANIEL VARNUM |
| METHANE-Subgrade | 12/26/2025 | Approved | DANIEL VARNUM |
| Smoke Detectors | 12/26/2025 | Approved | DANIEL VARNUM |
| Final | 12/30/2025 | OK to Issue CofO | DANIEL VARNUM |