3819 S 3RD AVE 90008

Certificate Information: 3819 S 3RD AVE 90008

Application / Permit
25014-10000-02097
Plan Check / Job No.
B25LA19048
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition and Remodel to (E) Single Family Dwelling. New Deck (223 sf) in the rear
Permit Issued
Issued on 7/18/2025
Issuing Office
Current Status
CofO Issued on 2/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2025 APPLICANT
Assigned to Plan Check Engineer 5/14/2025 AMY GUEVARRA
Corrections Issued 5/21/2025 AMY GUEVARRA
Applicant returned to address corrections 6/24/2025 AMY GUEVARRA
Plan Check Approved 6/27/2025 AMY GUEVARRA
Issued 7/18/2025 APPLICANT
CofO in Progress 2/23/2026 LUIS CASTRO
No Progress 2/23/2026 MICHAEL LEWIS
CofO in Progress 2/23/2026 MICHAEL LEWIS
Permit Finaled 2/26/2026 DEROLD HAUFF
CofO Issued 2/26/2026 DEROLD HAUFF
Permit Finaled 2/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 5/27/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 6/17/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 6/17/2025 JEREMY CHOK

Contact Information

Contractor 5 Blox Inc; Lic. No.: 1036356-B       ,
Contractor 5blox; Lic. No.: 1036356-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21731 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 9/9/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/15/2025 Partial Approval LUIS CASTRO
Insulation 9/15/2025 Approved LUIS CASTRO
Wood Frame 9/15/2025 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 10/2/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Partial Approval LUIS CASTRO
Drywall Nailing 11/19/2025 No Access for Inspection ANTHONY RAMOS
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready LUIS CASTRO
BUILDING-Rough-Frame 2/12/2026 Approved LUIS CASTRO
Final 2/12/2026 Corrections Issued LUIS CASTRO
Green Building Final 2/12/2026 Not Ready for Inspection LUIS CASTRO
Green Building Rough 2/12/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 2/12/2026 SGSOV Approved LUIS CASTRO
Smoke Detectors 2/12/2026 Corrections Issued LUIS CASTRO
ELECTRICAL-Final 2/19/2026 Approved LUIS CASTRO
Final 2/19/2026 OK to Issue CofO LUIS CASTRO
Green Building Final 2/19/2026 Approved LUIS CASTRO
HVAC-Final 2/19/2026 Approved LUIS CASTRO
PLUMBING-Final 2/19/2026 Approved LUIS CASTRO
Smoke Detectors 2/19/2026 Approved LUIS CASTRO