3059 W GLENHURST AVE 90039
Certificate Information: 3059 W GLENHURST AVE 90039
- Application / Permit
- 25014-10000-02050
- Plan Check / Job No.
- B25LA18591
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: (N) 1 STORY ADDITION TO EXISTING 2-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 5/29/2025
- Issuing Office
- Current Status
- CofO Issued on 10/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2025 | KELVIN CHUONG |
| Corrections Issued | 5/13/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/22/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 5/29/2025 | LUISANGEL VALENZUELA |
| Issued | 5/29/2025 | APPLICANT |
| CofO in Progress | 10/15/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 10/16/2025 | DEROLD HAUFF |
| CofO Issued | 10/16/2025 | DEROLD HAUFF |
| Permit Finaled | 10/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/15/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/15/2025 | DAVID LOPEZ |
| ZI | Cleared | 5/21/2025 | YINGSHI HUANG |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Precise Home Builders Inc; Lic. No.: 515469-B | , |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 6/17/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Partial Approval | JOSH MEISTER |
| PLUMBING-Rough | 6/23/2025 | Partial Approval | JOSH MEISTER |
| ELECTRICAL-Rough | 7/8/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Conditional Approval | NICHOLAS LOPEZ |
| HVAC-Rough | 7/8/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 7/8/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 7/9/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Rough | 7/9/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Insulation | 7/16/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 7/16/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 7/17/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 7/21/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 7/24/2025 | Approved | BRENDAN MORELLI |
| Shower Pan | 7/29/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 7/31/2025 | Approved | GEM DE OCAMPO |
| Special/Order Compliance | 8/14/2025 | Partial Approval | NICHOLAS LOPEZ |
| Final | 9/24/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 9/24/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 9/24/2025 | Approved | NICHOLAS LOPEZ |
| Final | 9/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 9/26/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Final | 10/14/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/14/2025 | SGSOV Approved | NICHOLAS LOPEZ |