3059 W GLENHURST AVE 90039

Certificate Information: 3059 W GLENHURST AVE 90039

Application / Permit
25014-10000-02050
Plan Check / Job No.
B25LA18591
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: (N) 1 STORY ADDITION TO EXISTING 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 5/29/2025
Issuing Office
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2025 APPLICANT
Assigned to Plan Check Engineer 5/12/2025 KELVIN CHUONG
Corrections Issued 5/13/2025 KELVIN CHUONG
Applicant returned to address corrections 5/22/2025 ARAMIK SHAHMIRZAIAN
Plan Check Approved 5/29/2025 LUISANGEL VALENZUELA
Issued 5/29/2025 APPLICANT
CofO in Progress 10/15/2025 NICHOLAS LOPEZ
Permit Finaled 10/16/2025 DEROLD HAUFF
CofO Issued 10/16/2025 DEROLD HAUFF
Permit Finaled 10/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/15/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 5/15/2025 DAVID LOPEZ
Sewer availability Cleared 5/15/2025 DAVID LOPEZ
ZI Cleared 5/21/2025 YINGSHI HUANG

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Precise Home Builders Inc; Lic. No.: 515469-B       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/11/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/17/2025 Partial Approval NICHOLAS LOPEZ
PLUMBING-Rough 6/17/2025 Partial Approval NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Partial Approval JOSH MEISTER
PLUMBING-Rough 6/23/2025 Partial Approval JOSH MEISTER
ELECTRICAL-Rough 7/8/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Conditional Approval NICHOLAS LOPEZ
HVAC-Rough 7/8/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 7/8/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 7/9/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Rough 7/9/2025 Not Ready for Inspection BRENDAN MORELLI
Insulation 7/16/2025 Corrections Issued NICHOLAS LOPEZ
Interior/Exterior Lathing 7/16/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 7/17/2025 Approved NICHOLAS LOPEZ
Green Building Rough 7/17/2025 Approved NICHOLAS LOPEZ
Insulation 7/21/2025 Approved ALEX COLIN
Drywall Nailing 7/24/2025 Approved BRENDAN MORELLI
Shower Pan 7/29/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 7/31/2025 Approved GEM DE OCAMPO
Special/Order Compliance 8/14/2025 Partial Approval NICHOLAS LOPEZ
Final 9/24/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/24/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 9/24/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 9/24/2025 Approved NICHOLAS LOPEZ
Final 9/26/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 9/26/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Not Ready NICHOLAS LOPEZ
Final 10/14/2025 OK to Issue CofO NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Approved NICHOLAS LOPEZ