1847 N FANNING ST 90026

Certificate Information: 1847 N FANNING ST 90026

Application / Permit
25014-10000-02047
Plan Check / Job No.
B25LA18561
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan addition portion of unfinished first floor to be part of (E) SFD with attached garage and remodel portion of the SFD
Permit Issued
Issued on 7/24/2025
Issuing Office
Current Status
CofO Issued on 5/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 GEORGE JOLAKIAN
Corrections Issued 5/20/2025 GEORGE JOLAKIAN
Quality Review Completed 6/6/2025 HERNAN ARREOLA
Applicant returned to address corrections 7/23/2025 GEORGE JOLAKIAN
Plan Check Approved 7/24/2025 GEORGE JOLAKIAN
Issued 7/24/2025 APPLICANT
CofO in Progress 5/28/2026 ALIZAH MAYAGOITIA
CofO in Progress 5/28/2026 ALIZAH MAYAGOITIA
Permit Finaled 5/30/2026 DEROLD HAUFF
CofO Issued 5/30/2026 DEROLD HAUFF
Permit Finaled 5/30/2026 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 6/9/2025 JASON CHAN
BHO/Hillside ordinance Cleared 6/14/2025 CINDY QI
BHO/Hillside ordinance Cleared 6/14/2025 CINDY QI
Roof/Waste drainage to street Cleared 6/14/2025 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/16/2025 CINDY QI
Sewer availability Cleared 6/16/2025 CINDY QI
Hydrant and Access approval Cleared 6/24/2025 JERRY KAO
BHO/Hillside ordinance Cleared 6/25/2025 ALBERT TAM
Grading Pre-Inspection Cleared 7/23/2025 RUSSELL BONVOULOIR

Contact Information

Architect Perella,, Ryan Adam; Lic. No.: NA30833       ,
Contractor Owner-Builder       ,
Engineer Sayah,, Daniel H; Lic. No.: NA67905       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Gas Test 10/14/2025 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 10/14/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 10/14/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/21/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/21/2025 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 10/21/2025 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/21/2025 Approved HAMIK HARTOUNIAN
Special/Order Compliance 10/21/2025 Partial Inspection OSVALDO PARAMO
BUILDING-Rough-Frame 10/27/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/12/2025 Partial Approval HAMIK HARTOUNIAN
Shower Pan 11/12/2025 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/2/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/12/2025 Approved GEM DE OCAMPO
Drywall Nailing 12/24/2025 Conditional Approval HAMIK HARTOUNIAN
Insulation 12/24/2025 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/29/2025 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 1/7/2026 Approved HAMIK HARTOUNIAN
Drywall Nailing 1/7/2026 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/7/2026 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 4/22/2026 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 4/22/2026 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 4/24/2026 No Access for Inspection ALIZAH MAYAGOITIA
Final 5/19/2026 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/19/2026 Approved HAMIK HARTOUNIAN
Green Building Final 5/19/2026 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/19/2026 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 5/19/2026 Approved HAMIK HARTOUNIAN
Final 5/27/2026 OK to Issue CofO HAMIK HARTOUNIAN
Final 5/28/2026 OK to Issue CofO ALIZAH MAYAGOITIA