3251 S BARRY AVE 90066

Certificate Information: 3251 S BARRY AVE 90066

Application / Permit
25014-10000-02018
Plan Check / Job No.
B25LA18311
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] Ground floor addition and Structural remodel to (E) 1-story single family dwelling with new attic area.
Permit Issued
Issued on 7/28/2025
Issuing Office
Current Status
Issued on 7/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/7/2025 APPLICANT
Assigned to Plan Check Engineer 5/8/2025 MAHNAZ NOURHASHEMI
Corrections Issued 5/14/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 5/20/2025 GARO TELMI
Applicant returned to address corrections 7/9/2025 MAHNAZ NOURHASHEMI
Plan Check Approved 7/24/2025 MAHNAZ NOURHASHEMI
Issued 7/28/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 6/5/2025 JOSHUA JONES
Grading Pre-Inspection Cleared 6/16/2025 LANNY MERRICK
Eng Process Fee Ord 176,300 Cleared 6/24/2025 VLADIMIR ARUTYUNYAN
Miscellaneous Cleared 6/24/2025 VLADIMIR ARUTYUNYAN
Roof/Waste drainage to street Cleared 6/24/2025 VLADIMIR ARUTYUNYAN
Sewer availability Cleared 6/24/2025 VLADIMIR ARUTYUNYAN
GPI Written Notices Cleared 7/24/2025 MAHNAZ NOURHASHEMI

Contact Information

Contractor Pure Builders Inc; Lic. No.: 757470-B       ,
Engineer Lewis,, Richard; Lic. No.: C90522 6044 HALM AVE      LOS ANGELES, CA 90056

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2025 Approved KIRK SANDERS
Deputy Drilled-In Anchors 9/19/2025 Conditional Approval KIRK SANDERS
BUILDING-Rough-Frame 10/16/2025 Partial Approval KIRK SANDERS
Insulation 10/16/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 10/16/2025 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/21/2025 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Corrections Issued EUGENE CASSIDY
Deputy Wood Construction 1/13/2026 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Partial Approval KIRK SANDERS
Green Building Rough 1/13/2026 Not Ready for Inspection KIRK SANDERS
Special/Order Compliance 1/13/2026 Corrections Issued KIRK SANDERS
PLUMBING-Rough 1/29/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 2/25/2026 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/13/2026 Approved JESUS PINEDA
Shower Pan 3/19/2026 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/2/2026 Partial Approval EUGENE CASSIDY
HVAC-Rough 4/7/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/13/2026 Approved MICHAEL ALLEN
Green Building Rough 4/13/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/21/2026 Approved ANDREW NAVE
Insulation 4/29/2026 Approved EUGENE CASSIDY
Drywall Nailing 5/12/2026 Approved ANDREW NAVE