933 S SYCAMORE AVE 90036
Certificate Information: 933 S SYCAMORE AVE 90036
- Application / Permit
- 25014-10000-01982
- Plan Check / Job No.
- B25LA18036
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePlan* Addition and remodel to existing 2-story duplex to convert to single family dwelling
- Permit Issued
- Issued on 8/21/2025
- Issuing Office
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2025 | MATTHEW TORRES |
| Corrections Issued | 5/21/2025 | MATTHEW TORRES |
| Quality Review Completed | 6/9/2025 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/1/2025 | MATTHEW TORRES |
| Applicant returned to address corrections | 8/14/2025 | MATTHEW TORRES |
| Plan Check Approved | 8/18/2025 | MATTHEW TORRES |
| Issued | 8/21/2025 | APPLICANT |
| CofO in Progress | 5/5/2026 | RONNIE MINDANAO |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
| CofO Issued | 5/8/2026 | DEROLD HAUFF |
| Permit Finaled | 5/8/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/10/2025 | DERRICK MAGEE |
| Address approval | Cleared | 6/12/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 6/12/2025 | DERRICK MAGEE |
| Demo/Removal of Rental Units | Cleared | 7/10/2025 | AMANDA POSTMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vega,, Cayetano Gonzalez; Lic. No.: NA43117 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/3/2025 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 10/3/2025 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 10/3/2025 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 10/8/2025 | Conditional Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/8/2025 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 10/29/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/31/2025 | Partial Approval | RONNIE MINDANAO |
| Gas Test | 10/31/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 10/31/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 11/4/2025 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 11/4/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 11/6/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 11/10/2025 | Approved | RONNIE MINDANAO |
| Deputy Wood Construction | 11/12/2025 | Conditional Approval | RONNIE MINDANAO |
| Green Building Rough | 11/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 11/12/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/18/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/19/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Rough | 11/19/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2025 | Not Ready for Inspection | JOSH MEISTER |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 11/25/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 12/2/2025 | Corrections Issued | JEFFREY MEAD |
| Insulation | 12/3/2025 | Conditional Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/3/2025 | Conditional Approval | RONNIE MINDANAO |
| Drywall Nailing | 12/11/2025 | Conditional Approval | ALEX COLIN |
| Green Building Rough | 12/11/2025 | Approved | ALEX COLIN |
| Drywall Nailing | 12/12/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 12/31/2025 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Rough | 1/7/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 1/9/2026 | Approved | JEFFREY MEAD |
| HVAC-Rough | 2/23/2026 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 3/20/2026 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 3/20/2026 | Approved | RONNIE MINDANAO |
| Gas Test | 3/25/2026 | Approved | RONNIE MINDANAO |
| HVAC-Final | 3/25/2026 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 4/1/2026 | Approved | JOSH MEISTER |
| HVAC-Final | 4/1/2026 | Approved | JOSH MEISTER |
| Drywall Nailing | 4/6/2026 | Approved | RONNIE MINDANAO |
| Final | 4/6/2026 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/6/2026 | Approved | RONNIE MINDANAO |
| Green Building Final | 4/6/2026 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/6/2026 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 4/6/2026 | Approved | RONNIE MINDANAO |
| Final | 4/16/2026 | Partial Approval | RONNIE MINDANAO |
| Final | 4/20/2026 | Partial Approval | RONNIE MINDANAO |
| Final | 4/28/2026 | OK to Issue CofO | RONNIE MINDANAO |
| Final | 4/30/2026 | Partial Approval | RONNIE MINDANAO |