13742 W CHASE ST 91331
Certificate Information: 13742 W CHASE ST 91331
- Application / Permit
- 25014-10000-01945
- Plan Check / Job No.
- B25LA17783
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) STORAGE INTO ADU W/(N) ADDITION (514 SQ FT) TOTAL PER STATE LAW
- Permit Issued
- Issued on 7/11/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2025 | NEHEMIAS RAMOS |
| Corrections Issued | 5/8/2025 | NEHEMIAS RAMOS |
| Building Plans Picked Up | 5/13/2025 | APPLICANT |
| Plan Check Approved | 7/8/2025 | NGHI SU |
| Issued | 7/11/2025 | APPLICANT |
| CofO in Progress | 12/15/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
| CofO Issued | 1/2/2026 | RUBEN SALAS |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 6/18/2025 | GEVORK KARAPETYAN |
| Construction within easement | Cleared | 6/18/2025 | GEVORK KARAPETYAN |
| Address approval | Cleared | 7/8/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2025 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 7/8/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/8/2025 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/29/2025 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/30/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 7/30/2025 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/12/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 8/12/2025 | Approved | KEVIN BERBERYAN |
| Gas Test | 8/12/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 8/12/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 8/12/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 8/12/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/18/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 8/21/2025 | Approved | MICHAEL CORTEZ |
| Gas Test | 8/21/2025 | Approved | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/1/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/10/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 12/10/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 12/10/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 12/10/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/10/2025 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/10/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/10/2025 | Approved | OGANES TARAKHCHYAN |